Preview only show first 10 pages with watermark. For full document please download

056-001 Four Steps To Synchronising

   EMBED


Share

Transcript

Four Simple Steps to Successful Synchronising and Load Sharing 1. Control a. Control of AVR b. Control of Governor c. Direction of Control 2. Metering a. CTs on the Right Phase b. CTs in the Right Direction 3. Communications a. All Modules Connected on the MSC Link b. Re-Calibrate, Sync + Load Control, Multi-Set c. Remove One MSC Plug 4. Sync Checks a. Use the Built in Sync Scope to Determine Correct Phase Wiring b. Phase Checks Across the Breaker. A Detailed description of each step is contained within Load Share Design and Commissioning, (DSE Part Number 057-047) 056-001 Issue 1 - Four Simple Steps