Transcript
PUBLIC WORKS DEPARTMENT
Project:
Benton City Road
Drainage Structure / Low Water Crossing
Precinct: 1 Location / Limits: Benton City Rd between Von Ormy Rd and Jackel Rd, Elm Creek..
Scope: Structure replacement will provide for an improved conveyance of storm water runoff while having no adverse impact to the existing 100-years level of Water Surface Elevation
Status: Complete
Additional Information: Consultant: HDR Engineering
Bid Opening: Feb. 14, 2014
Contractor: D Plata Construction LLC
Construction Start : 2 Q 2014
Construction Cost: $ 356,906.24
Construction End Date: 4 Q 2014
Joint Bid: None
With Flood Control Component
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Big Country Phase V
Precinct: 1 Location / Limits: Blue Mesa, Fort Wayne, Black River, Hatchet Pass, Jarbo Pass, Cache Path, Yurba Trail, Two Wells, Fish Springs, Olney Springs, Potter Valley, Muddy Peak, Crescent Peak and Mud Lake.
Scope: The main purpose of the project is to reconstruct 14 residential streets with curb & gutter section, 4-foot sidewalk including ADA complaint ramps and driveway approaches. SAWS joint bid with Bexar County to replace existing service service lines within the project.
Status: Construction
Additional Information: Consultants: LNV / In TEC
Bid Opening: May 3, 2013
Contractor: Olmos Equipment, Inc.
Construction Start : 3 Q 2013
Roadway Construction Cost: $ 5,729,172.71 Construction End Date: 2 Q 2015 Joint Bid : SAWS January 30, 2015
PUBLIC WORKS DEPARTMENT Project: FM 1957 Potranco Rd Precinct: 1 Location / Limits: Loop 1604 to just west of SH 211
Scope: Construction will provide for enhanced connection between two western relief routes of SH 211 and Loop 1604. The proposed improvements will expand the existing two-lane rural roadway section to an urban roadway section consisting of two 11-foot lanes, and two 14-foot shared use lanes, continuous left turn lane or 14-foot raised center median within an 80’ ROW (Minimum).
Status: Final Design , Utility Relocation / Adjustments
Additional Information: Consultants: Pape-Dawson / Jacobs
Advertise Date: 1 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 34,226,011
Construction End Date: 3 Q 2018
Joint Bid: CPS , SAWS
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: FM 471 Culebra Rd Precinct: 1 & 2 Location / Limits: From FM 1560 to Old FM 471.
Scope: The construction will complete the capacity gap that currently exists on FM 471 from FM 1560 to Old FM 471. The proposed improvements will widen Culebra Road from its existing two-lane configuration to a four-lane divided roadway with anticipated bicycle and pedestrian amenities.
Status: Final Design
Additional Information: Consultants: CP&Y / Atkins
Advertise Date: 2 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 14,719,463
Construction End Date: 4 Q 2016
Joint Bid: SAWS, CPS Gas.
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: Fischer Rd Phase I Precinct: 1 Location / Limits: From Quintana Rd to IH 35 S
Scope: Project will expand the existing twolane rural roadway section to an urban roadway section consisting of two 16-foot travel lanes in each direction with 6 ft. shoulders, curbs and sidewalks within an 86’ ROW (typical). -
2,100 L.F. No in flood plain. One culvert (pipe). Medio Creek Watershed.
Status: Preliminary.
Additional Information: Consultants: Garzabury LLC
Advertise Date: TBD
Contractor: TBD
Construction Start Date: TBD
Construction Cost: $ 1,890,000
Construction End Date: TBD
Joint Bid: TBD
Economic Development Project
January 30, 2015
PUBLIC WORKS DEPARTMENT Project:
Macdona Streets Reconstruction
Precinct: 1 Location / Limits: Macdona Subdivision in Southwest Bexar County, including next streets: Commerce St, Rockport St, Main St and 3, 4, 5, 6 & 7th St. ,
Scope: Reconstruction of 24’ rural roadway section and reestablishing positive drainage (9 streets).
Status: Complete
Additional Information: Consultants: CP & Y / Prof Serv. Ind.
Bid Opening: January 10, 2014
Contractor: Tropical Contracting Inc.
Construction Start: 3 Q 2014
Construction Cost: $ 2,464,000.00
Construction End Date: 1 Q 2015
Joint Bid: None January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: Precinct:
Old FM 471 & Talley Rd
1
Location / Limits: Old FM 471 starting and ending on FM 471 (Culebra Rd) and Talley Rd from FM 471 (Culebra Rd) to Old Talley Rd. (South End). Scope: Roadway expansion from 2 lanes to 3 lanes with curbs, sidewalks and drainage improvements due to new schools and development in the area.
Status: Preliminary
Additional Information: Consultant: Dannenbaum
Advertise Date:
Contractor: TBD
Construction Start Date:
Construction Cost: $ 10,000,000
Construction End Date: TBD
Joint Bid: TBD January 30, 2015
TBD TBD
PUBLIC WORKS DEPARTMENT
Project:
Roft Rd
Precinct: 1 Location / Limits: From Culebra Rd to Rockwall Mill Rd. (5,100 L.F.)
Scope: This project will expand the existing two-lane rural roadway section to a mixed rural/urban roadway section with curb & sidewalks on the east side of the roadway and drainage improvements.
Status: Intermediate Design
Additional Information: Consultant: ARCADIS
Advertise Date: 3 Q 2016
Contractor: TBD
Construction Start Date: 4 Q 2016
Construction Cost: $ 3,100,000
Construction End Date: 4 Q 2017
Joint Bid: TBD January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: SH 211 Precinct: 1 Location / Limits: From FM 1957 (Potranco Rd) to FM 471 (Culebra Rd)
Scope: The proposed project would construct a new two-lane roadway connecting the existing sections of SH 211 from FM 471 (Culebra Road) to FM 1957 (Potranco Road). The purpose of the proposed project is to improve connectivity and mobility, and provide residents a through alternative between FM 1957 and FM 471. The total length of the project is 7.6 miles.
Status: Alternatives Analysis / Environmental.
Additional Information: Consultant: Pape-Dawson
Advertise Date: 3 Q 2015
Contractor: TBD
Construction Start Date: 4 Q 2015
Construction Cost: $ 18,100,000
Construction End Date: 3 Q 2017
Joint Bid: N/A
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: Talley Rd – FM 957 (Potranco Rd) to Wiseman Blvd. Precinct: 1 Location / Limits: From FM 1957 (Potranco Rd) to Wiseman Blvd.
Scope: Roadway expansion from 2 to 4 lanes with curbs, sidewalks, bike lanes, turn lanes and drainage improvements. Some ROW acquisition will be required.
Status: Preliminary.
Additional Information: Consultant: CP & Y
Advertise Date:
Contractor: TBD
Construction Start Date:
Construction Cost: $ 12,500,000
Construction End Date: TBD
Joint Bid: TBD January 30, 2015
TBD TBD
PUBLIC WORKS DEPARTMENT
Project:
West Military Bridge Ext
Precinct: 1 Location / Limits: West Military Bridge Extension
Scope: Project consist of construction of mirror image of existing 32 ft. X 400 ft. bridge parallel over Medio Creek stripping to accommodate bike lanes and travel lane each direction and 5 foot sidewalk. The project included the adjustment / relocate / replacement of CPS gas within the project limits.
Status: Complete.
Additional Information: Consultants: SEA / HJV Assoc / Arias
Bid Opening: Aug 6, 2012
Contractor: Relmco
Construction Start: 3 Q 2012
Construction Cost: $ 1,589,168
Construction End Date: 2 Q 2014
Joint Bid: CPS. January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Watson Rd Phase I
Precinct: 1 Location / Limits: From Somerset Road to SWISD
Scope: Watson Rd is currently a 2 lane roadway and will be reconstructed to include 4-12’ travel lanes, drainage improvements and pedestrian amenities.
Status: Planning.
Additional Information: Consultants: TBD
Bid Opening: TBD
Contractor: TBD
Construction Start: TBD
Construction Cost: $ 6,800,000
Construction End Date: TBD
Joint Bid: TBD
MPO Project
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: WT Montgomery Road Phase I Precinct: 1 Location / Limits: IH 90 West to Lucas Creek bridge.
Scope: The main purpose of the project is to provide much needed drainage improvements and road reconstruction to the WT Montgomery Road.
Status: Final Design
Additional Information: Consultant:
IDC, Inc.
Advertise Date: 2 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 5,671,000
Construction End Date: 4 Q 2016
Joint Bid: TBD January 30, 2015