Transcript
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Star t Duration
ENSDSA1000
Shop drawing submit tal
ENSDSA1010
Shop drawing approval
PROCUREMENT MATERIAL SUBMITTAL SUBMI
Finish
30 29-Jun-14 A
31-Jul-14 A
21 03-Aug-14 A
Total Pocess Delays
Total Float SI- 1
31-Aug-14 A
-12
280 25-May-14 A 28-Feb-15 A
-81
55 25-May-14 A 18-Jul-14 A
-41
Readymix concrete
7 25-May-14 A 31 3 1-May-14 A
0
EMS1010
St eel reinforcement
7 25-May-14 A 31 3 1-May-14 A
0
EMS10100
Pipe bedding
7 25-May-14 A
31 31-May-14 A
0
EMS1070
Epoxy Products
7 01-Jun-14 A
07-Jun-14 A
0
EMS1080
Tanking
7 01-Jun-14 A
07 07-Jun-14 A
0
EMS1090
Bitumen Primer
7 01-Jun-14 A
07-Jun-14 A
0
EMS1120
DI Manhole Cover & Frame
7 01-Jun-14 A
07-Jun-14 A
0
EMS1130
Surface Box
7 01-Jun-14 A
07-Jun-14 A
0
EMS10600
Marker/ warning tape
7 01-Jun-14 A
07-Jun-14 A
0
EMS1100
6mm Plywood
7 01-Jun-14 A
07-Jun-14 A
0
EMS1040
VC Pipe & Fitt ings
7 12-Jul-14 A
18-Jul-14 A
-48
SI -1
EMS1050
GRP Lined RC Jacking Pipes
7 12-Jul-14 A
18-Jul-14 A
-48
SI -1
EMS1060
GRP Products
SI -1
7 12-Jul-14 A
18-Jul-14 A
-48
56 01-Jun-14 A
20-Aug-14 A
-30
EMA1000
Readymix concrete
21 01-Jun-14 A
29-Jun-14 A
0
EMA1010
St eel reinforcement
21 01-Jun-14 A
29-Jun-14 A
0
EMA10100
Pipe bedding
21 01-Jun-14 A
29-Jun-14 A
0
EMA1070
Epoxy Products
21 08-Jun-14 A
06-Jul-14 A
0
EMA1080
Tanking
21 08-Jun-14 A
06 06-Jul-14 A
0
EMA1090
Bitumen Primer
21 08-Jun-14 A
06-Jul-14 A
0
EMA1100
6mm Plywood
21 08-Jun-14 A
06-Jul-14 A
0
EMA1120
DI Manhole Cover & Frame
21 08-Jun-14 A
06-Jul-14 A
0
EMA1130
Surface Box
21 08-Jun-14 A
06-Jul-14 A
0
EMA10600
Marker/ warning tape
21 08-Jun-14 A
06-Jul-14 A
EMA1050
GRP Lined RC Jacking Pipes
21 20-Jul-14 A
20-Aug-14 A
-35
SI -1
EMA1060
GRP Products
21 20-Jul-14 A
20-Aug-14 A
-35
SI -1
EMA1040
VC Pipe & Fitt ings
SI -1
PROCURE MATER MATERIAL
Remaining Level of Effort Actual Level of Effort Effort Primary Baseline
Second Baseline
Criti...
Actual Work
Mile...
Remaining ng W ork
Date
Rev ision
Mar
Apr
May
Jun
Jul
0
21 20-Jul-14 A
20-Aug-14 A
-35
63 30-Jun-14 A
03-Sep-14 A
-42
Checked
2015 Feb
-18
EMS1000
MATERIAL APPROVAL APPR
SI-2
Approv ed
Document Tittle: Progress Update as per Revised Programme 02 Page 3 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
Total Pocess Delays
PMP1000
Readymix concrete
14 30-Jun-14 A
13-Jul-14 A
0
PMP1010
Steel reinforcement & Formwork
14 30-Jun-14 A
13-Jul-14 A
0
PMP10100
Pipe bedding
14 30-Jun-14 A
13-Jul-14 A
0
PMP1070
Epoxy Products
14 07-Jul-14 A
20-Jul-14 A
0
PMP1080
Tanking
14 07-Jul-14 A
20-Jul-14 A
0
PMP1090
Bitumen Primer
14 07-Jul-14 A
20-Jul-14 A
0
PMP1100
6mm Plywood
14 07-Jul-14 A
20-Jul-14 A
0
PMP1120
DI Manhole Cover & Frame
14 07-Jul-14 A
20-Jul-14 A
0
PMP1130
Surface Box
14 07-Jul-14 A
20-Jul-14 A
0
20-Jul-14 A
Total Float SI-1
Marker/warning tape
14 07-Jul-14 A
PMP1040
VC Pipe & Fittings
14 21-Aug-14 A 03-Sep-14 A
-49
SI-1
PMP1060
GRP Products
14 21-Aug-14 A
-49
SI-1
PMP1050
GRP Lined RC Jacking Pipes
14 21-Aug-14 A
MATERIAL DELIVERY DELIV TO SITE
03-Sep-14 A
-49
236 30-Jun-14 A
28-Feb-15 A
-79
Readymix concrete
157 30-Jun-14 A
09-Dec-14 A
0
PMD1050
GRP Lined RC Jacking Pipes
141 21-Aug-14 A
12-Jan-15 A
-50
PMD1010
Steel reinforcement
236 30-Jun-14 A
28-Feb-15 A
-86
PMD1040
VC Pipe & Fittings
187 21-Aug-14 A 28-Feb-15 A
-91
SI-1
PMD1060
GRP Products
187 21-Aug-14 A
28-Feb-15 A
-124
SI-1
PMD1070
Epoxy Products
229 07-Jul-14 A
28-Feb-15 A
-204
PMD1080
Tanking
229 07-Jul-14 A
28-Feb-15 A
-128
PMD1090
Bitumen Primer
229 07-Jul-14 A
28-Feb-15 A
-175
PMD1100
6mm Plywood
229 07-Jul-14 A
28-Feb-15 A
-182
PMD10100
Pipe bedding
236 30-Jun-14 A
28-Feb-15 A
-222
PMD1120
DI Manhole Cover & Frame
229 07-Jul-14 A
28-Feb-15 A
-215
PMD1130
Surface Box
229 07-Jul-14 A
28-Feb-15 A
-215
PMD10600
Marker/warning tape
229 07-Jul-14 A
28-Feb-15 A
-124
359 29-Jun-14 A
22-Jun-15 A
-184
359 29-Jun-14 A
22-Jun-15 A
-196
287 29-Jun-14 A
11-Apr-15 A
-216
283 29-Jun-14 A
07-Apr-15 A
-238
219 29-Jun-14 A
19-Mar-15 A
-198
SEWER IN TRENCH TRENC PHASE 1: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 VC PIP PIPE E WORK WORKS: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 200mm NOMINAL NOMIN BORE 33.88m: From MH 15/1/28/12/6 to MH 15/1/28/12/5
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
0
PMD1000
CONSTRUCTION
2015 Feb
PMP10600
03-Sep-14 A
SI-2
SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 4 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
4 22-Nov-14 A
CST1220
Excavation & disposal of materials
CST1230
Bedding preparation prior to VC pipe laying
3 27-Nov-14 A
30-Nov-14 A
-101
CST1240
Laying VC pipes & fittings and pre-testing
2 04-Dec-14 A
06-Dec-14 A
-104
CST1250
Granular & concrete surrounds
2 09-Dec-14 A
10-Dec-14 A
-106
CST1260
Backfilling
4 10-Dec-14 A
14-Dec-14 A
-106
CST1270
SRC 20 concrete backfill
2 17-Dec-14 A
20-Dec-14 A
-108
CST1350
Marker tape installation
2 18-Mar-15 A
19-Mar-15 A
-183
88 10-Jan-15 A
07-Apr-15 A
-238
-180
300mm NOMINAL NOMIN BORE 59.46m: From MH 15/1/28/12/1 to MH 15/1/28/12
25-Nov-14 A
Total Pocess Delays
Recovery
0 10-Jan-15 A
CST1290
Excavation & disposal of materials
2 01-Mar-15 A
02-Mar-15 A
75 10-Jan-15 A
25-Mar-15 A
Delay: Issuance of Excavation permit
CST1300
Bedding preparation prior to VC pipe laying
4 28-Mar-15 A
31-Mar-15 A
-203
CST1310
Laying VC pipes & fittings and pre-testing
5 28-Mar-15 A
01-Apr-15 A
-202
CST1320
Granular & concrete surrounds
6 28-Mar-15 A
02-Apr-15 A
-201
CST1330
Backfilling
7 28-Mar-15 A
04-Apr-15 A
-199
CST1340
SRC 20 concrete backfill
8 29-Mar-15 A
06-Apr-15 A
-199
CST1420
Marker tape installation
1 07-Apr-15 A
07-Apr-15 A
-199
46 16-Feb-15 A
09-Apr-15 A
46 16-Feb-15 A
09-Apr-15 A
1 16-Mar-15 A
16-Mar-15 A 05-Apr-15 A
CST2330
SRC 20 concrete backfill
CST2280
Excavation & disposal of materials
42 16-Feb-15 A
CST2290
Bedding preparation prior to VC pipe laying
40 18-Feb-15 A
05-Apr-15 A
CST2300
Laying VC pipes & fittings and pre-testing
39 19-Feb-15 A
05-Apr-15 A
CST2310
Granular & concrete surrounds
38 21-Feb-15 A
05-Apr-15 A
CST2320
Backfilling
38 22-Feb-15 A
06-Apr-15 A
CST2340
Marker tape installation
2 08-Apr-15 A
MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/12/6
29-Mar-15 A
-178
25 26-Jul-14 A
26-Aug-14 A
-14
Excavation & disposal of materials
4 26-Jul-14 A
02-Aug-14 A
-14
CSTM1020
Blinding
1 03-Aug-14 A
03-Aug-14 A
-14
CSTM1030
Reinforcement, shuttering, concreting
4 04-Aug-14 A
07-Aug-14 A
-14
CSTM1040
Pipe connection to manhole & pre-testing of section
2 09-Aug-14 A
10-Aug-14 A
-14
Remaining Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
09-Apr-15 A
204 26-Jul-14 A
CSTM1010
Actual Level of Effort
2015 Feb
-99
CST129.10
FC-01
SI-2
ery
CST129
FUTURE CONNE CONNECTION
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 6 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
Total Pocess Delays
CSTM10400
Benching work
2 11-Aug-14 A
12-Aug-14 A
-14
CSTM1050
Bitumen primer
1 13-Aug-14 A
13-Aug-14 A
-14
CSTM1060
Tanking membrane
1 14-Aug-14 A
14-Aug-14 A
-14
CSTM1070
Epoxy mortor & sealant
2 16-Aug-14 A
17-Aug-14 A
-14
CSTM1080
GRP accessories
2 18-Aug-14 A
19-Aug-14 A
-14
CSTM1090
DI Manhole Cover & Frame
2 20-Aug-14 A
21-Aug-14 A
-14
CSTM1100
Backfilling
3 23-Aug-14 A 25-Aug-14 A
-14
CSTM1330
SRC 20 concrete backfill
1 26-Aug-14 A
26-Aug-14 A
-14
25 03-Aug-14 A
31-Aug-14 A
MANHOLE: 15/1 15/1/28/12/5 CSTM28210
Excavation & disposal of materials
4 03-Aug-14 A
06-Aug-14 A
CSTM28220
Blinding
1 07-Aug-14 A
07-Aug-14 A
CSTM28230
Reinforcement, shuttering, concreting
4 09-Aug-14 A
12-Aug-14 A
CSTM28240
Pipe connection to manhole & pre-testing of section
2 13-Aug-14 A
14-Aug-14 A
CSTM28250
Benching work
2 16-Aug-14 A
17-Aug-14 A
CSTM28260
Bitumen primer
1 18-Aug-14 A
18-Aug-14 A
CSTM28270
Tanking membrane
1 19-Aug-14 A
19-Aug-14 A
CSTM28280
Epoxy mortor & sealant
2 20-Aug-14 A
21-Aug-14 A
CSTM28290
GRP accessories
2 23-Aug-14 A
24-Aug-14 A
CSTM28300
DI Manhole Cover & Frame
2 25-Aug-14 A
26-Aug-14 A
CSTM28310
Backfilling
3 27-Aug-14 A
30-Aug-14 A
CSTM28320
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/12/4
1 31-Aug-14 A
31-Aug-14 A
24 21-Aug-14 A
17-Sep-14 A
Excavation & disposal of materials
4 21-Aug-14 A
25-Aug-14 A
-34
CSTM1360
Blinding
1 26-Aug-14 A
26-Aug-14 A
-34
CSTM1370
Reinforcement, shuttering, concreting
4 27-Aug-14 A
31-Aug-14 A
-34
CSTM1380
Pipe connection to manhole & pre-testing of section
2 01-Sep-14 A
02-Sep-14 A
-32
CSTM13800
Benching work
2 03-Sep-14 A
04-Sep-14 A
-32
CSTM1390
Bitumen primer
1 06-Sep-14 A
06-Sep-14 A
-32
CSTM1400
Tanking membrane
1 07-Sep-14 A
07-Sep-14 A
-32
CSTM1410
Epoxy mortor & sealant
1 08-Sep-14 A
08-Sep-14 A
-32
CSTM1420
GRP accessories
2 09-Sep-14 A
10-Sep-14 A
-32
CSTM1430
DI Manhole Cover & Frame
2 11-Sep-14 A
13-Sep-14 A
-32
Remaining Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
-32
CSTM1350
Actual Level of Effort
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 7 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
CSTM1440
Backfilling
CSTM1450
SRC 20 concrete backfill
Finish
3 14-Sep-14 A 16-Sep-14 A
MANHOLE: 15/1 15/1/28/12/3
Total Pocess Delays
1 17-Sep-14 A
17-Sep-14 A
-32
32 17-Aug-14 A
22-Sep-14 A
-32
Excavation & disposal of materials
4 17-Aug-14 A
20-Aug-14 A
-25
CSTM1480
Blinding
1 28-Aug-14 A
28-Aug-14 A
-31
CSTM1490
Reinforcement, shuttering, concreting
4 01-Sep-14 A
04-Sep-14 A
-33
CSTM1500
Pipe connection to manhole & pre-testing of section
2 06-Sep-14 A
07-Sep-14 A
-32
CSTM15000
Benching work
2 08-Sep-14 A
09-Sep-14 A
-32
CSTM1510
Bitumen primer
1 10-Sep-14 A
10-Sep-14 A
-32
CSTM1520
Tanking membrane
1 11-Sep-14 A
11-Sep-14 A
-32
CSTM1530
Epoxy mortor & sealant
1 13-Sep-14 A
13-Sep-14 A
-32
CSTM1540
GRP accessories
2 14-Sep-14 A
15-Sep-14 A
-32
CSTM1550
DI Manhole Cover & Frame
2 16-Sep-14 A
17-Sep-14 A
-32
CSTM1560
Backfilling
3 18-Sep-14 A 21-Sep-14 A
-32
CSTM1570
SRC 20 concrete backfill
1 22-Sep-14 A
22-Sep-14 A
27 21-Dec-14 A
20-Jan-15 A
SRC 20 concrete backfill
1 21-Dec-14 A
21-Dec-14 A
-96
Excavation & disposal of materials
4 25-Dec-14 A
29-Dec-14 A
-123
CSTM1600
Blinding
1 30-Dec-14 A
30-Dec-14 A
-123
CSTM1610
Reinforcement, shuttering, concreting
4 31-Dec-14 A
04-Jan-15 A
-123
CSTM1620
Pipe connection to manhole & pre-testing of section
2 05-Jan-15 A
06-Jan-15 A
-123
CSTM16200
Benching work
2 07-Jan-15 A
08-Jan-15 A
-123
CSTM1630
Bitumen primer
1 10-Jan-15 A
10-Jan-15 A
-123
CSTM1640
Tanking membrane
1 11-Jan-15 A
11-Jan-15 A
-123
CSTM1650
Epoxy mortor & sealant
1 12-Jan-15 A
12-Jan-15 A
-123
CSTM1660
GRP accessories
2 13-Jan-15 A
14-Jan-15 A
-123
CSTM1670
DI Manhole Cover & Frame
2 15-Jan-15 A
17-Jan-15 A
-123
CSTM1680
Backfilling
3 18-Jan-15 A
20-Jan-15 A
-123 -178
81 24-Dec-14 A
29-Mar-15 A
CSTM1710
Excavation & disposal of materials
4 24-Dec-14 A
28-Dec-14 A
-122
CSTM1720
Blinding
2 28-Dec-14 A
29-Dec-14 A
-122
CSTM1730
Reinforcement, shuttering, concreting
4 31-Dec-14 A
04-Jan-15 A
-123
Remaining Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
-32
CSTM1590
Actual Level of Effort
2015 Feb
-122
CSTM1690
MANHOLE: 15/1 15/1/28/12/1
SI-2
-32
CSTM1470
MANHOLE: 15/1 15/1/28/12/2
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 8 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
CSTM1740
Original Start Duration
Pipe connection to manhole & pre-testing of section
Finish
3 05-Jan-15 A
07-Jan-15 A
Total Pocess Delays
Benching work
2 08-Jan-15 A
10-Jan-15 A
-124
CSTM1750
Bitumen primer
1 13-Jan-15 A
13-Jan-15 A
-126
CSTM1760
Tanking membrane
1 29-Jan-15 A
29-Jan-15 A
-139
CSTM1770
Epoxy mortor & sealant
1 25-Feb-15 A
25-Feb-15 A
-160
CSTM1780
GRP accessories
2 26-Feb-15 A
28-Feb-15 A
-160
CSTM1800
Backfilling
4 24-Feb-15 A
28-Feb-15 A
-155
CSTM1790
DI Manhole Cover & Frame
3 21-Mar-15 A
23-Mar-15 A
-178
CSTM1810
SRC 20 concrete backfill
3 26-Mar-15 A
29-Mar-15 A
-178
79 25-Dec-14 A
28-Mar-15 A
CSTM28330
Excavation & disposal of materials
5 25-Dec-14 A
30-Dec-14 A
CSTM28340
Blinding
1 01-Jan-15 A
01-Jan-15 A
CSTM28350
Reinforcement, shuttering, concreting
4 03-Jan-15 A
06-Jan-15 A
CSTM28360
Pipe connection to manhole & pre-testing of section
2 07-Jan-15 A
08-Jan-15 A
CSTM28370
Benching work
2 10-Jan-15 A
11-Jan-15 A
CSTM28380
Bitumen primer
1 12-Jan-15 A
12-Jan-15 A
CSTM28390
Tanking membrane
1 13-Jan-15 A
13-Jan-15 A
CSTM28400
Epoxy mortor & sealant
2 19-Mar-15 A
21-Mar-15 A
CSTM28410
GRP accessories
3 21-Mar-15 A
23-Mar-15 A
CSTM28420
DI Manhole Cover & Frame
3 23-Mar-15 A
25-Mar-15 A
CSTM28430
Backfilling
4 24-Mar-15 A
28-Mar-15 A
CSTM28440
SRC 20 concrete backfill
REINSTATEMENT ASPHALT
2 26-Mar-15 A
28-Mar-15 A
41 23-Feb-15 A
11-Apr-15 A
-180
39 23-Feb-15 A
08-Apr-15 A
-182 -186
CSTR1110
90mm Base course
38 23-Feb-15 A
07-Apr-15 A
CSTR1120
70mm Wearing course
27 09-Mar-15 A
08-Apr-15 A
-182
18 22-Mar-15 A
11-Apr-15 A
-186
KERBSTONE CSTR1130
Excavation & concrete foundation for kerbs
16 22-Mar-15 A
08-Apr-15 A
-186
CSTR1140
Kerbs installation
17 22-Mar-15 A
09-Apr-15 A
-186
CSTR1150
Backing concrete
18 22-Mar-15 A
11-Apr-15 A
-186
2 18-Mar-15 A
19-Mar-15 A
-163
2 18-Mar-15 A
19-Mar-15 A
-165
PAVING/ CONCRETE PAVING PAVING/CONCR CSTR1160
Formation preparation
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
-124
CSTM17400
MANHOLE: 15/1 15/1/28/12
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 9 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
CST2220
Bedding preparation prior to VC pipe laying
11 11-Feb-15 A
CST2230
Laying VC pipes & fittings and pre-testing
11 11-Feb-15 A
24-Feb-15 A
CST2240
Granular & concrete surrounds
11 11-Feb-15 A
24-Feb-15 A
CST2250
Backfilling
11 11-Feb-15 A
24-Feb-15 A
CST2260
SRC 20 concrete backfill
10 14-Feb-15 A
24-Feb-15 A
CST2270
Marker tape installation
300mm NOMIN NOMINAL BORE 71.5m: From MH 15/1/28/14 to MH 15/1/28/15
Total Pocess Delays
2 17-Mar-15 A
18-Mar-15 A
180 16-Aug-14 A
18-Mar-15 A
-148 15
Excavation & disposal of materials
5 16-Aug-14 A
20-Aug-14 A
CST1370
Bedding preparation prior to VC pipe laying
5 26-Aug-14 A
31-Aug-14 A
8
CST1380
Laying VC pipes & fittings and pre-testing
3 28-Aug-14 A
31-Aug-14 A
10
CST1390
Granular & concrete surrounds
2 31-Aug-14 A
01-Sep-14 A
11
CST1400
Backfilling
3 02-Sep-14 A
04-Sep-14 A
11
CST1410
SRC 20 concrete backfill
3 06-Sep-14 A
08-Sep-14 A
10
CST1490
Marker tape installation
2 17-Mar-15 A
18-Mar-15 A
-148
153 16-Sep-14 A
18-Mar-15 A
-145
CST1430
Excavation & disposal of materials
134 16-Sep-14 A
24-Feb-15 A
-141
CST1440
Bedding preparation prior to VC pipe laying
130 21-Sep-14 A
24-Feb-15 A
-139
CST1450
Laying VC pipes & fittings and pre-testing
131 23-Sep-14 A
28-Feb-15 A
-140
CST1460
Granular & concrete surrounds
129 25-Sep-14 A
28-Feb-15 A
-136
CST1470
Backfilling
127 28-Sep-14 A
28-Feb-15 A
-132
CST1480
SRC 20 concrete backfill
124 01-Oct-14 A
28-Feb-15 A
-130
CST1560
Marker tape installation
2 17-Mar-15 A
18-Mar-15 A
-145
70 18-Feb-15 A
10-May-15 A
FUTURE CONNE CONNECTION
46 18-Feb-15 A
12-Apr-15 A
CST2350
Excavation & disposal of materials
14 18-Feb-15 A
05-Mar-15 A
CST2360
Bedding preparation prior to VC pipe laying
12 21-Feb-15 A
06-Mar-15 A
CST2370
Laying VC pipes & fittings and pre-testing
11 22-Feb-15 A
06-Mar-15 A
CST2380
Granular & concrete surrounds
11 23-Feb-15 A
07-Mar-15 A
CST2390
Backfilling
10 24-Feb-15 A
07-Mar-15 A
CST2400
SRC 20 concrete backfill
1 09-Apr-15 A
09-Apr-15 A
CST2410
Marker tape installation
2 11-Apr-15 A
12-Apr-15 A
45 21-Feb-15 A
13-Apr-15 A
FC-02
FC-03
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
24-Feb-15 A
CST1360
300mm NOMINAL NOMIN BORE 60m: From MH 15/1/28/15 to MH 15/1/28/16
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 11 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
CST2420
Excavation & disposal of materials
12 21-Feb-15 A
CST2430
Bedding preparation prior to VC pipe laying
11 23-Feb-15 A
07-Mar-15 A
CST2440
Laying VC pipes & fittings and pre-testing
10 24-Feb-15 A
07-Mar-15 A
CST2450
Granular & concrete surrounds
10 25-Feb-15 A
08-Mar-15 A
CST2460
Backfilling
9 26-Feb-15 A
08-Mar-15 A
CST2470
SRC 20 concrete backfill
1 11-Apr-15 A
11-Apr-15 A
CST2480
Marker tape installation
1 12-Apr-15 A
13-Apr-15 A
66 23-Feb-15 A
10-May-15 A 05-Apr-15 A
FC-04 Excavation & disposal of materials
36 23-Feb-15 A
CST2500
Bedding preparation prior to VC pipe laying
34 25-Feb-15 A
05-Apr-15 A
CST2510
Laying VC pipes & fittings and pre-testing
34 26-Feb-15 A
06-Apr-15 A
CST2520
Granular & concrete surrounds
33 28-Feb-15 A
06-Apr-15 A
CST2530
Backfilling
33 28-Feb-15 A
06-Apr-15 A
CST2540
SRC 20 concrete backfill
24 12-Apr-15 A
09-May-15 A
CST2550
Marker tape installation
24 13-Apr-15 A
10-May-15 A
29 08-Mar-15 A
09-Apr-15 A 06-Apr-15 A
CST2560
Excavation & disposal of materials
26 08-Mar-15 A
CST2570
Bedding preparation prior to VC pipe laying
23 11-Mar-15 A
06-Apr-15 A
CST2580
Laying VC pipes & fittings and pre-testing
22 12-Mar-15 A
06-Apr-15 A
CST2590
Granular & concrete surrounds
21 14-Mar-15 A
06-Apr-15 A
CST2600
Backfilling
21 14-Mar-15 A
06-Apr-15 A
CST2610
SRC 20 concrete backfill
21 16-Mar-15 A
08-Apr-15 A
CST2620
Marker tape installation
20 18-Mar-15 A
09-Apr-15 A
98 01-Dec-14 A
26-Mar-15 A
73 03-Dec-14 A
28-Feb-15 A
MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/13 CSTM28450
Excavation & disposal of materials
4 03-Dec-14 A
07-Dec-14 A
CSTM28460
Blinding
2 08-Dec-14 A
09-Dec-14 A
CSTM28470
Reinforcement, shuttering, concreting
5 08-Dec-14 A
13-Dec-14 A
CSTM28480
Pipe connection to manhole & pre-testing of section
3 15-Dec-14 A
17-Dec-14 A
CSTM28490
Benching work
3 20-Dec-14 A
22-Dec-14 A
CSTM28500
Bitumen primer
2 23-Dec-14 A
24-Dec-14 A
CSTM28510
Tanking membrane
1 02-Feb-15 A
02-Feb-15 A
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Total Float SI-1
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
06-Mar-15 A
CST2490
FC-05
Total Pocess Delays
-140
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 12 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
CSTM28520
Epoxy mortor & sealant
1 03-Feb-15 A
03-Feb-15 A
CSTM28530
GRP accessories
2 04-Feb-15 A
05-Feb-15 A
CSTM28550
Backfilling
3 09-Feb-15 A
11-Feb-15 A
CSTM28560
SRC 20 concrete backfill
2 18-Feb-15 A
19-Feb-15 A
CSTM28540
DI Manhole Cover & Frame
2 26-Feb-15 A
28-Feb-15 A
71 04-Dec-14 A
26-Feb-15 A
MANHOLE: 15/1 15/1/28/14 CSTM28570
Excavation & disposal of materials
4 04-Dec-14 A
08-Dec-14 A
CSTM28580
Blinding
2 11-Dec-14 A
13-Dec-14 A
CSTM28590
Reinforcement, shuttering, concreting
4 14-Dec-14 A
17-Dec-14 A
CSTM28600
Pipe connection to manhole & pre-testing of section
2 17-Dec-14 A
20-Dec-14 A
CSTM28610
Benching work
3 21-Dec-14 A
23-Dec-14 A
CSTM28620
Bitumen primer
2 08-Jan-15 A
10-Jan-15 A
CSTM28630
Tanking membrane
2 12-Jan-15 A
13-Jan-15 A
CSTM28640
Epoxy mortor & sealant
1 14-Jan-15 A
14-Jan-15 A
CSTM28650
GRP accessories
2 15-Jan-15 A
17-Jan-15 A
CSTM28670
Backfilling
3 04-Feb-15 A
07-Feb-15 A
CSTM28680
SRC 20 concrete backfill
2 19-Feb-15 A
21-Feb-15 A
CSTM28660
DI Manhole Cover & Frame
2 25-Feb-15 A
26-Feb-15 A
31 22-Jan-15 A
28-Feb-15 A
MANHOLE: 15/1 15/1/28/14/1 CSTM28690
Excavation & disposal of materials
4 22-Jan-15 A
26-Jan-15 A
CSTM28700
Blinding
1 02-Feb-15 A
02-Feb-15 A
CSTM28710
Reinforcement, shuttering, concreting
4 03-Feb-15 A
07-Feb-15 A
CSTM28720
Pipe connection to manhole & pre-testing of section
2 08-Feb-15 A
09-Feb-15 A
CSTM28730
Benching work
2 10-Feb-15 A
11-Feb-15 A
CSTM28740
Bitumen primer
1 14-Feb-15 A
14-Feb-15 A
CSTM28750
Tanking membrane
1 15-Feb-15 A
15-Feb-15 A
CSTM28760
Epoxy mortor & sealant
1 16-Feb-15 A
16-Feb-15 A
CSTM28770
GRP accessories
2 17-Feb-15 A
18-Feb-15 A
CSTM28790
Backfilling
3 22-Feb-15 A
24-Feb-15 A
CSTM28800
SRC 20 concrete backfill
1 25-Feb-15 A
25-Feb-15 A
CSTM28780
DI Manhole Cover & Frame
1 27-Feb-15 A
28-Feb-15 A
32 21-Jan-15 A
28-Feb-15 A
MANHOLE: 15/1 15/1/28/14/2
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Total Pocess Delays
Total Float SI-1
SI-2
2015 Feb
Approved
Mar
Apr
May
Jun
Jul
Document Tittle: Progress Update as per Revised Programme 02 Page 13 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
CSTM28810
Excavation & disposal of materials
4 21-Jan-15 A
25-Jan-15 A
CSTM28820
Blinding
1 02-Feb-15 A
02-Feb-15 A
CSTM28830
Reinforcement, shuttering, concreting
4 03-Feb-15 A
07-Feb-15 A
CSTM28840
Pipe connection to manhole & pre-testing of section
2 08-Feb-15 A
09-Feb-15 A
CSTM28850
Benching work
2 10-Feb-15 A
11-Feb-15 A
CSTM28860
Bitumen primer
1 14-Feb-15 A
14-Feb-15 A
CSTM28870
Tanking membrane
1 15-Feb-15 A
15-Feb-15 A
CSTM28880
Epoxy mortor & sealant
1 16-Feb-15 A
16-Feb-15 A
CSTM28890
GRP accessories
2 17-Feb-15 A
18-Feb-15 A
CSTM28910
Backfilling
3 22-Feb-15 A
24-Feb-15 A
CSTM28920
SRC 20 concrete backfill
1 26-Feb-15 A
26-Feb-15 A
CSTM28900
DI Manhole Cover & Frame
2 26-Feb-15 A
28-Feb-15 A
75 01-Dec-14 A
28-Feb-15 A
MANHOLE: 15/1 15/1/28/15
Total Pocess Delays
Excavation & disposal of materials
4 01-Dec-14 A
04-Dec-14 A
-70
CSTM1960
Blinding
2 06-Dec-14 A
07-Dec-14 A
-71
CSTM1970
Reinforcement, shuttering, concreting
5 09-Dec-14 A
14-Dec-14 A
-73
CSTM1980
Pipe connection to manhole & pre-testing of section
3 15-Dec-14 A
17-Dec-14 A
-74
CSTM19800
Benching work
3 17-Dec-14 A
21-Dec-14 A
-74
CSTM1990
Bitumen primer
2 24-Dec-14 A
25-Dec-14 A
-77
CSTM2000
Tanking membrane
2 27-Dec-14 A
28-Dec-14 A
-78
CSTM2010
Epoxy mortor & sealant
1 08-Feb-15 A
08-Feb-15 A
-113
CSTM2020
GRP accessories
2 09-Feb-15 A
10-Feb-15 A
-113
CSTM2040
Backfilling
3 15-Feb-15 A
17-Feb-15 A
-113
CSTM2030
DI Manhole Cover & Frame
2 26-Feb-15 A
28-Feb-15 A
-125
CSTM2050
SRC 20 concrete backfill
1 28-Feb-15 A
28-Feb-15 A
-121
45 02-Feb-15 A
26-Mar-15 A
-140
CSTM2070
Excavation & disposal of materials
3 02-Feb-15 A
04-Feb-15 A
-122
CSTM2080
Blinding
1 05-Feb-15 A
05-Feb-15 A
-122
CSTM2090
Reinforcement, shuttering, concreting
4 07-Feb-15 A
10-Feb-15 A
-122
CSTM2100
Pipe connection to manhole & pre-testing of section
2 11-Feb-15 A
14-Feb-15 A
-118
CSTM21000
Benching work
2 15-Feb-15 A
16-Feb-15 A
-118
CSTM2110
Bitumen primer
1 17-Feb-15 A
17-Feb-15 A
-118
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
-121
CSTM1950
MANHOLE: 15/1 15/1/28/16
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 14 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
1 18-Feb-15 A
CSTM2120
Tanking membrane
CSTM2130
Epoxy mortor & sealant
1 19-Feb-15 A
19-Feb-15 A
-118
CSTM2140
GRP accessories
2 21-Feb-15 A
22-Feb-15 A
-118
CSTM2160
Backfilling
3 25-Feb-15 A
28-Feb-15 A
-118
CSTM2170
SRC 20 concrete backfill
3 25-Feb-15 A
28-Feb-15 A
-117
CSTM2150
DI Manhole Cover & Frame
2 25-Mar-15 A
26-Mar-15 A
-144
54 11-Feb-15 A
15-Apr-15 A
-141
54 11-Feb-15 A
15-Apr-15 A
-147
49 11-Feb-15 A
09-Apr-15 A
-147
6 09-Apr-15 A
15-Apr-15 A
-147
2 09-Apr-15 A
11-Apr-15 A
-145
REINSTATEMENT ASPHALT CSTR1010
90mm Base course
CSTR1020
70mm Wearing course
KERBSTONE
18-Feb-15 A
Total Pocess Delays
Excavation & concrete foundation for kerbs
2 09-Apr-15 A
11-Apr-15 A
-147
CSTR1040
Kerbs installation
2 09-Apr-15 A
11-Apr-15 A
-146
CSTR1050
Backing concrete
2 09-Apr-15 A
11-Apr-15 A
-145
3 09-Apr-15 A
12-Apr-15 A
-142
CSTR1060
Formation preparation
3 09-Apr-15 A
12-Apr-15 A
-144
CSTR1070
Paving interlock
3 09-Apr-15 A
12-Apr-15 A
-142 -140
5 09-Apr-15 A
14-Apr-15 A
CSTR1080
Excavation for plants
3 09-Apr-15 A
12-Apr-15 A
-140
CSTR1090
Planting/grass
3 12-Apr-15 A
14-Apr-15 A
-140
PHASE 3: FROM MH 15/1/28/17 TO 15/1/28/25
155 19-Jan-15 A
22-Jun-15 A
-196
VC PIPE WORK WORKS: 15/1/28/17 TO 15/1/28/21
127 16-Feb-15 A
22-Jun-15 A
-217
55 19-Feb-15 A
14-Apr-15 A
-195 -137
PLANT AND GR GRASS
300mm NOMINAL NOMIN BORE 70m: From MH 15/1/28/16 to MH 15/1/28/17 CST1500
Excavation & disposal of materials
10 19-Feb-15 A
02-Mar-15 A
CST1510
Bedding preparation prior to VC pipe laying
1 28-Mar-15 A
28-Mar-15 A
-157
CST1520
Laying VC pipes & fittings and pre-testing
1 28-Mar-15 A
28-Mar-15 A
-155
CST1530
Granular & concrete surrounds
1 28-Mar-15 A
28-Mar-15 A
-153
CST1540
Backfilling
1 12-Apr-15 A
12-Apr-15 A
-191
CST1550
SRC 20 concrete backfill
1 13-Apr-15 A
13-Apr-15 A
-190
CST1630
Marker tape installation
1 14-Apr-15 A
14-Apr-15 A
-190
39 12-Apr-15 A
30-May-15 A
-198
200mm NOMIN NOMINAL BORE 45.93m: From MH 15/1/28/17 to MH 15/1/28/18 0000.30
As per Al Jazeera, TCTC shall be allowed to work
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Revision
Checked
2015 Feb
Mar
Apr
May
Jun
Jul
Aug
As per Al Jazeera, TCTC shall be allowe
0 12-Apr-15 A
Date
SI-2
-118
CSTR1030
PAVING/ CONCRETE PAVING PAVING/CONCR
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 15 of 35 Data Date: 22-Jun-15
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
CST1840
Original Start Duration
Marker tape installation
Finish
Total Pocess Delays
2 29-Mar-15 A
30-Mar-15 A
-133
27 22-Feb-15 A
24-Mar-15 A
-107
CST1780
Excavation & disposal of materials
11 22-Feb-15 A
05-Mar-15 A
-100
CST1790
Bedding preparation prior to VC pipe laying
11 24-Feb-15 A
08-Mar-15 A
-101
CST1800
Laying VC pipes & fittings and pre-testing
1 14-Mar-15 A
14-Mar-15 A
-104
CST1810
Granular & concrete surrounds
1 15-Mar-15 A
15-Mar-15 A
-104
CST1820
Backfilling
1 24-Mar-15 A
24-Mar-15 A
-109
CST1910
Marker tape installation
1 24-Mar-15 A
24-Mar-15 A
-107
CST1830
SRC 20 concrete backfill
1 24-Mar-15 A
24-Mar-15 A
-108
11 04-Apr-15 A
14-Apr-15 A
11 04-Apr-15 A
14-Apr-15 A 05-Apr-15 A
200mm NOMIN NOMINAL BORE 14.68m: From MH 15/1/28/20 to MH 15/1/28/21
FUTURE CONNE CONNECTION FC-06 CST2980
Excavation & disposal of materials
2 04-Apr-15 A
CST2990
Bedding preparation prior to VC pipe laying
1 06-Apr-15 A
06-Apr-15 A
CST3000
Laying VC pipes & fittings and pre-testing
1 07-Apr-15 A
07-Apr-15 A
CST3010
Granular & concrete surrounds
1 09-Apr-15 A
09-Apr-15 A
CST3020
Backfilling
1 11-Apr-15 A
11-Apr-15 A
CST3030
SRC 20 concrete backfill
1 12-Apr-15 A
12-Apr-15 A
CST3040
Marker tape installation
2 13-Apr-15 A
14-Apr-15 A
152 19-Jan-15 A
19-Jun-15 A
-197
38 09-Mar-15 A
15-Apr-15 A
-179
MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/17 CSTM2190
Excavation & disposal of materials
1 09-Mar-15 A
09-Mar-15 A
-140
CSTM2200
Blinding
1 10-Mar-15 A
10-Mar-15 A
-140
CSTM2210
Reinforcement, shuttering, concreting
1 11-Mar-15 A
11-Mar-15 A
-137
CSTM2220
Pipe connection to manhole & pre-testing of section
1 12-Mar-15 A
12-Mar-15 A
-136
CSTM22200
Benching work
1 12-Mar-15 A
12-Mar-15 A
-134
CSTM2230
Bitumen primer
1 14-Mar-15 A
14-Mar-15 A
-134
CSTM2240
Tanking membrane
1 14-Mar-15 A
14-Mar-15 A
-133
CSTM2250
Epoxy mortor & sealant
1 14-Mar-15 A
14-Mar-15 A
-132
CSTM2260
GRP accessories
1 12-Apr-15 A
12-Apr-15 A
-181
CSTM2270
DI Manhole Cover & Frame
1 13-Apr-15 A
13-Apr-15 A
-180
CSTM2280
Backfilling
1 14-Apr-15 A
14-Apr-15 A
-178
CSTM2290
SRC 20 concrete backfill
1 15-Apr-15 A
15-Apr-15 A
-177
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Total Float SI-1
SI-2
2015 Feb
Approved
Mar
Apr
May
Jun
Jul
Document Tittle: Progress Update as per Revised Programme 02 Page 17 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
MANHOLE: 15/1 15/1/28/18
Finish
120 19-Jan-15 A
18-May-15 A 22-Feb-15 A
Total Pocess Delays
Delay: Issuance of Excavation permit
35 19-Jan-15 A
0000.20
Delay: Al Jazeera Stopped the Work
37 23-Feb-15 A
31-Mar-15 A
CSTM2310
Excavation & disposal of materials
2 12-Apr-15 A
13-Apr-15 A
CSTM2320
Blinding/Tanking & Screeding
3 14-Apr-15 A
16-Apr-15 A
CSTM2330
Reinforcement, shuttering, concreting (Base & Wall)
4 01-May-15 A 04-May-15 A
CSTM2340
Pipe connection to manhole & Backdrob
4 05-May-15 A 08-May-15 A
-178
CSTM23400
Bitumen primer
1 09-May-15 A 09-May-15 A
-177
CSTM2350
Tanking membrane
1 10-May-15 A 10-May-15 A
-177
CSTM2360
Backfilling
4 11-May-15 A 14-May-15 A
-180
CSTM2370
DI Manhole Cover & Frame
1 15-May-15 A 15-May-15 A
-179
CSTM2380
SRC 20 concrete backfill
1 16-May-15 A 16-May-15 A
-178
CSTM2390
Benching work
1 17-May-15 A 17-May-15 A
-177
CSTM2410
GRP accessories
1 18-May-15 A 18-May-15 A
-173
19 12-Apr-15 A
30-Apr-15 A
CSTM29290
Excavation & disposal of materials
2 12-Apr-15 A
13-Apr-15 A
CSTM29300
Blinding/Tanking & Screeding
3 14-Apr-15 A
16-Apr-15 A
CSTM29310
Reinforcement, shuttering, concreting (Base & Wall)
4 17-Apr-15 A
20-Apr-15 A
CSTM29320
Pipe connection to manhole & Backdrob
4 21-Apr-15 A
24-Apr-15 A
CSTM29330
Bitumen primer
1 25-Apr-15 A
25-Apr-15 A
CSTM29340
Tanking membrane
1 26-Apr-15 A
26-Apr-15 A
CSTM29350
Backfilling
4 27-Apr-15 A
30-Apr-15 A
CSTM29360
DI Manhole Cover & Frame
1 30-Apr-15 A
30-Apr-15 A
CSTM29370
SRC 20 concrete backfill
1 30-Apr-15 A
30-Apr-15 A
CSTM29380
Benching work
1 30-Apr-15 A
30-Apr-15 A
CSTM29390
GRP accessories
1 30-Apr-15 A
30-Apr-15 A
SI-2
May
Jun
Jul
-163 -177
Excavation & disposal of materials
2 28-May-15 A 29-May-15 A
SI-2
CSTM29420
Blinding/Tanking & Screeding
3 30-May-15 A 01-Jun-15 A
SI-2
CSTM29430
Reinforcement, shuttering, concreting (Base & Wall)
4 02-Jun-15 A
05-Jun-15 A
SI-2
CSTM29440
Pipe connection to manhole & Backdrob
4 06-Jun-15 A
09-Jun-15 A
SI-2
CSTM29450
Bitumen primer
1 10-Jun-15 A
10-Jun-15 A
SI-2
Primary Baseline
Apr
-161
CSTM29410
Remaining Level of Effort
Mar
23 28-May-15 A 19-Jun-15 A
MANHOLE: 15/1 15/1/28/19/1
Actual Level of Effort
2015 Feb
-175
0000.10
MANHOLE: 15/1 15/1/28/19
Total Float SI-1
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 18 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
Total Pocess Delays
Total Float SI-1
SI-2
CSTM29460
Tanking membrane
1 11-Jun-15 A
11-Jun-15 A
SI-2
CSTM29470
Backfilling
4 12-Jun-15 A
15-Jun-15 A
SI-2
CSTM29480
DI Manhole Cover & Frame
1 16-Jun-15 A
16-Jun-15 A
SI-2
CSTM29490
SRC 20 concrete backfill
1 17-Jun-15 A
17-Jun-15 A
SI-2
CSTM29500
Benching work
1 18-Jun-15 A
18-Jun-15 A
SI-2
CSTM29510
GRP accessories
1 19-Jun-15 A
19-Jun-15 A
SI-2
63 16-Feb-15 A
19-Apr-15 A
CSTM2550
Excavation & disposal of materials
2 16-Feb-15 A
17-Feb-15 A
-85
CSTM2560
Blinding
2 24-Mar-15 A
25-Mar-15 A
-115
CSTM2570
Reinforcement, shuttering, concreting
1 25-Mar-15 A
25-Mar-15 A
-111
CSTM2580
Pipe connection to manhole & pre-testing of section
2 28-Mar-15 A
29-Mar-15 A
-112
MANHOLE: 15/1 15/1/28/20
Benching work
1 12-Apr-15 A
12-Apr-15 A
-143
CSTM2590
Bitumen primer
1 13-Apr-15 A
13-Apr-15 A
-143
CSTM2600
Tanking membrane
1 14-Apr-15 A
14-Apr-15 A
-143
CSTM2610
Epoxy mortor & sealant
1 15-Apr-15 A
15-Apr-15 A
-142
CSTM2620
GRP accessories
1 16-Apr-15 A
16-Apr-15 A
-141
CSTM2630
DI Manhole Cover & Frame
1 17-Apr-15 A
17-Apr-15 A
-140
CSTM2640
Backfilling
1 18-Apr-15 A
18-Apr-15 A
-137
CSTM2650
SRC 20 concrete backfill
1 19-Apr-15 A
19-Apr-15 A
-137
66 14-Feb-15 A
20-Apr-15 A
-137
CSTM2670
Excavation & disposal of materials
13 14-Feb-15 A
28-Feb-15 A
-91
CSTM2680
Blinding
1 12-Mar-15 A
12-Mar-15 A
-101
CSTM2690
Reinforcement, shuttering, concreting
2 15-Mar-15 A
16-Mar-15 A
-100
CSTM2700
Pipe connection to manhole & pre-testing of section
1 26-Mar-15 A
26-Mar-15 A
-107
CSTM27000
Benching work
1 13-Apr-15 A
13-Apr-15 A
-140
CSTM2710
Bitumen primer
1 14-Apr-15 A
14-Apr-15 A
-140
CSTM2720
Tanking membrane
1 15-Apr-15 A
15-Apr-15 A
-140
CSTM2730
Epoxy mortor & sealant
1 16-Apr-15 A
16-Apr-15 A
-140
CSTM2740
GRP accessories
1 17-Apr-15 A
17-Apr-15 A
-139
CSTM2750
DI Manhole Cover & Frame
1 18-Apr-15 A
18-Apr-15 A
-137
CSTM2760
Backfilling
1 19-Apr-15 A
19-Apr-15 A
-135
CSTM2770
SRC 20 concrete backfill
1 20-Apr-15 A
20-Apr-15 A
-135
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
-139
CSTM25800
MANHOLE: 15/1 15/1/28/21
2015 Feb
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 19 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
CSMJ1150
Original Start Duration
Jacking GRP lined RC pipe
Finish
9 13-Sep-14 A
22-Sep-14 A
Total Pocess Delays
Testing Prior to Annulus Grouting
1 23-Sep-14 A
23-Sep-14 A
-38
CSMJ1160
Annulus grouting
1 24-Sep-14 A
24-Sep-14 A
-38
22 23-Sep-14 A
21-Oct-14 A
-44
CSMJ1190
Excavation for receiver shaft
9 23-Sep-14 A
02-Oct-14 A
-44
CSMJ1200
Concrete for platform & trust wall
1 07-Oct-14 A
07-Oct-14 A
-44
CSMJ1210
Jacking GRP lined RC pipe
10 08-Oct-14 A
19-Oct-14 A
-44
CSMJ12100
Testing Prior to Annulus Grouting
1 20-Oct-14 A
20-Oct-14 A
-44
CSMJ1220
Annulus grouting
1 21-Oct-14 A
21-Oct-14 A
-44
MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/1
187 25-Sep-14 A
30-Mar-15 A
-182
123 27-Nov-14 A
29-Mar-15 A
-222
CSMM1840
Preparing shaft for MH construction
2 27-Nov-14 A
29-Nov-14 A
-107
CSMM1850
Blinding
1 30-Nov-14 A
30-Nov-14 A
-107
CSMM184
Recovery
0 10-Jan-15 A
CSMM1860
Reinforcement, shuttering, concreting
44 01-Dec-14 A
21-Jan-15 A
CSMM1870
Pipe connection to manhole & pre-testing of section
3 21-Jan-15 A
24-Jan-15 A
-146
CSMM18700
Benching work
2 31-Jan-15 A
01-Feb-15 A
-151
CSMM1880
Bitumen primer
1 02-Feb-15 A
02-Feb-15 A
-151
CSMM1890
Tanking membrane
1 03-Feb-15 A
03-Feb-15 A
-151
CSMM1900
Epoxy mortor & sealant
1 04-Feb-15 A
04-Feb-15 A
-151
CSMM1930
Backfilling
3 23-Feb-15 A
25-Feb-15 A
-159
CSMM1910
GRP accessories
2 25-Feb-15 A
26-Feb-15 A
-167
CSMM1920
DI Manhole Cover & Frame
3 23-Mar-15 A
25-Mar-15 A
-188
CSMM1940
SRC 20 concrete backfill
3 26-Mar-15 A
29-Mar-15 A
-185 -137
122 25-Sep-14 A
19-Feb-15 A
1 25-Sep-14 A
25-Sep-14 A
-38
CSMM1960
Blinding
1 27-Sep-14 A
27-Sep-14 A
-38
CSMM1970
Reinforcement, shuttering, concreting
96 28-Sep-14 A
21-Jan-15 A
-130
CSMM1980
Pipe connection to manhole & pre-testing of section
3 26-Jan-15 A
28-Jan-15 A
-134
CSMM19800
Benching work
2 02-Feb-15 A
03-Feb-15 A
-137
CSMM1990
Bitumen primer
1 04-Feb-15 A
04-Feb-15 A
-137
CSMM2000
Tanking membrane
1 05-Feb-15 A
05-Feb-15 A
-137
Remaining Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
-147
Preparing shaft for MH construction
Actual Level of Effort
2015 Feb
ery
CSMM1950
MANHOLE: 15/1 15/1/28/2
SI-2
-38
CSMJ11500
300mm NOMIN NOMINAL BORE IN M.TUNNEL70m: From MH 15/1/28/3 to MH 15/1/28/4
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 21 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
Total Pocess Delays
CSMM2010
Epoxy mortor & sealant
1 07-Feb-15 A
07-Feb-15 A
-137
CSMM2020
GRP accessories
2 08-Feb-15 A
09-Feb-15 A
-137
CSMM2030
DI Manhole Cover & Frame
2 10-Feb-15 A
11-Feb-15 A
-137
CSMM2040
Backfilling
5 14-Feb-15 A
18-Feb-15 A
-137
CSMM2050
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/3
1 19-Feb-15 A
19-Feb-15 A
-137
103 22-Oct-14 A
21-Feb-15 A
-125
CSMJ1840
Preparing shaft for MH construction
1 22-Oct-14 A
22-Oct-14 A
-44
CSMJ1850
Blinding
1 23-Oct-14 A
23-Oct-14 A
-44
CSMJ1860
Reinforcement, shuttering, concreting
76 25-Oct-14 A
21-Jan-15 A
-116
CSMJ1870
Pipe connection to manhole & pre-testing of section
3 31-Jan-15 A
02-Feb-15 A
-124
CSMJ18700
Benching work
2 04-Feb-15 A
05-Feb-15 A
-125
CSMJ1880
Bitumen primer
1 07-Feb-15 A
07-Feb-15 A
-125
CSMJ1890
Tanking membrane
1 08-Feb-15 A
08-Feb-15 A
-125
CSMJ1900
Epoxy mortor & sealant
1 09-Feb-15 A
09-Feb-15 A
-125
CSMJ1910
GRP accessories
1 10-Feb-15 A
10-Feb-15 A
-125
CSMJ1920
DI Manhole Cover & Frame
2 11-Feb-15 A
14-Feb-15 A
-125
CSMJ1930
Backfilling
5 15-Feb-15 A
19-Feb-15 A
-125
CSMJ1940
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/4
1 21-Feb-15 A
21-Feb-15 A
-125
72 05-Jan-15 A
30-Mar-15 A
-151
CSMJ1950
Preparing shaft for MH construction
2 05-Jan-15 A
06-Jan-15 A
-102
CSMJ1960
Blinding
2 18-Jan-15 A
19-Jan-15 A
-112
CSMJ1970
Reinforcement, shuttering, concreting
4 04-Feb-15 A
08-Feb-15 A
-125
CSMJ1980
Pipe connection to manhole & pre-testing of section
2 09-Feb-15 A
10-Feb-15 A
-125
CSMJ19800
Benching work
2 11-Feb-15 A
14-Feb-15 A
-125
CSMJ1990
Bitumen primer
1 15-Feb-15 A
15-Feb-15 A
-125
CSMJ2000
Tanking membrane
1 16-Feb-15 A
16-Feb-15 A
-125
CSMJ2010
Epoxy mortor & sealant
1 17-Feb-15 A
17-Feb-15 A
-125
CSMJ2020
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-131
CSMJ2040
Backfilling
4 24-Feb-15 A
28-Feb-15 A
-126
CSMJ2030
DI Manhole Cover & Frame
3 26-Mar-15 A
29-Mar-15 A
-156
CSMJ2050
SRC 20 concrete backfill
REINSTATEMENT
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
3 28-Mar-15 A
30-Mar-15 A
-151
12 16-Mar-15 A
29-Mar-15 A
-134
Checked
Total Float SI-1
SI-2
2015 Feb
Approved
Mar
Apr
May
Jun
Jul
Document Tittle: Progress Update as per Revised Programme 02 Page 22 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
MANHOLE CON CONSTRUCTION
Finish
Total Pocess Delays
86 17-Dec-14 A
29-Mar-15 A
-103 -144
79 27-Dec-14 A
29-Mar-15 A
CSMJ2060
Preparing shaft for MH construction
2 27-Dec-14 A
28-Dec-14 A
-88
CSMJ2070
Blinding
1 20-Jan-15 A
20-Jan-15 A
-107
CSMJ2080
Reinforcement, shuttering, concreting
4 31-Jan-15 A
03-Feb-15 A
-115
CSMJ2090
Pipe connection to manhole & pre-testing of section
2 15-Feb-15 A
16-Feb-15 A
-123
CSMJ20900
Benching work
2 17-Feb-15 A
18-Feb-15 A
-123
CSMJ2100
Bitumen primer
1 19-Feb-15 A
19-Feb-15 A
-123
CSMJ2110
Tanking membrane
1 21-Feb-15 A
21-Feb-15 A
-123
CSMJ2120
Epoxy mortor & sealant
1 22-Feb-15 A
22-Feb-15 A
-123
CSMJ2130
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-125
CSMJ2150
Backfilling
6 22-Feb-15 A
28-Feb-15 A
-120
CSMJ2160
SRC 20 concrete backfill
3 25-Mar-15 A
28-Mar-15 A
-143
CSMJ2140
DI Manhole Cover & Frame
MANHOLE: 15/1 15/1/28/5
MANHOLE: 15/1 15/1/28/6
3 26-Mar-15 A
29-Mar-15 A
-150
72 04-Jan-15 A
29-Mar-15 A
-137
CSMJ2170
Preparing shaft for MH construction
2 04-Jan-15 A
05-Jan-15 A
-88
CSMJ2180
Blinding
2 27-Jan-15 A
28-Jan-15 A
-107
CSMJ2190
Reinforcement, shuttering, concreting
4 31-Jan-15 A
03-Feb-15 A
-108
CSMJ2200
Pipe connection to manhole & pre-testing of section
2 04-Feb-15 A
05-Feb-15 A
-108
CSMJ22000
Benching work
2 07-Feb-15 A
08-Feb-15 A
-108
CSMJ2210
Bitumen primer
1 09-Feb-15 A
09-Feb-15 A
-108
CSMJ2220
Tanking membrane
1 10-Feb-15 A
10-Feb-15 A
-108
CSMJ2230
Epoxy mortor & sealant
1 11-Feb-15 A
11-Feb-15 A
-108
CSMJ2240
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-118
CSMJ2260
Backfilling
6 22-Feb-15 A
28-Feb-15 A
-113
CSMJ2250
DI Manhole Cover & Frame
3 25-Mar-15 A
28-Mar-15 A
-142
CSMJ2270
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/7
3 26-Mar-15 A
29-Mar-15 A
-137
75 31-Dec-14 A
29-Mar-15 A
-131 -76
CSMJ2300
Reinforcement, shuttering, concreting
4 31-Dec-14 A
04-Jan-15 A
CSMJ2310
Pipe connection to manhole & pre-testing of section
3 05-Jan-15 A
07-Jan-15 A
-77
CSMJ23100
Benching work
2 08-Jan-15 A
10-Jan-15 A
-77
CSMJ2280
Preparing shaft for MH construction
2 12-Jan-15 A
13-Jan-15 A
-89
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Total Float SI-1
SI-2
2015 Feb
Approved
Mar
Apr
May
Jun
Jul
Document Tittle: Progress Update as per Revised Programme 02 Page 25 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
Total Pocess Delays
CSMJ2320
Bitumen primer
2 13-Jan-15 A
14-Jan-15 A
-80
CSMJ2290
Blinding
2 27-Jan-15 A
28-Jan-15 A
-101
CSMJ2330
Tanking membrane
1 31-Jan-15 A
31-Jan-15 A
-93
CSMJ2340
Epoxy mortor & sealant
1 01-Feb-15 A
01-Feb-15 A
-93
CSMJ2350
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-112
CSMJ2370
Backfilling
5 23-Feb-15 A
28-Feb-15 A
-107
CSMJ2360
DI Manhole Cover & Frame
3 26-Mar-15 A
29-Mar-15 A
-137
CSMJ2380
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/8
3 26-Mar-15 A
29-Mar-15 A
-131
74 01-Jan-15 A
29-Mar-15 A
-125 -73
CSMJ2400
Blinding
2 01-Jan-15 A
03-Jan-15 A
CSMJ2410
Reinforcement, shuttering, concreting
4 04-Jan-15 A
07-Jan-15 A
-73
CSMJ2390
Preparing shaft for MH construction
2 08-Jan-15 A
10-Jan-15 A
-80
CSMJ2420
Pipe connection to manhole & pre-testing of section
3 07-Jan-15 A
10-Jan-15 A
-73
CSMJ24200
Benching work
2 10-Jan-15 A
11-Jan-15 A
-72
CSMJ2430
Bitumen primer
2 11-Jan-15 A
12-Jan-15 A
-72
CSMJ2440
Tanking membrane
1 31-Jan-15 A
31-Jan-15 A
-87
CSMJ2450
Epoxy mortor & sealant
1 01-Feb-15 A
01-Feb-15 A
-87
CSMJ2460
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-106
CSMJ2480
Backfilling
6 22-Feb-15 A
28-Feb-15 A
-101
CSMJ2470
DI Manhole Cover & Frame
3 26-Mar-15 A
29-Mar-15 A
-131
CSMJ2490
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/9
3 26-Mar-15 A
29-Mar-15 A
-125
86 17-Dec-14 A
29-Mar-15 A
-119
CSMJ2510
Blinding
2 17-Dec-14 A
20-Dec-14 A
-55
CSMJ2520
Reinforcement, shuttering, concreting
5 22-Dec-14 A
27-Dec-14 A
-57
CSMJ2530
Pipe connection to manhole & pre-testing of section
2 29-Dec-14 A
30-Dec-14 A
-58
CSMJ25300
Benching work
2 01-Jan-15 A
03-Jan-15 A
-59
CSMJ2500
Preparing shaft for MH construction
2 04-Jan-15 A
05-Jan-15 A
-70
CSMJ2540
Bitumen primer
2 05-Jan-15 A
06-Jan-15 A
-61
CSMJ2550
Tanking membrane
1 31-Jan-15 A
31-Jan-15 A
-81
CSMJ2560
Epoxy mortor & sealant
1 01-Feb-15 A
01-Feb-15 A
-81
CSMJ2570
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-100
CSMJ2590
Backfilling
6 23-Feb-15 A
01-Mar-15 A
-96
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Total Float SI-1
SI-2
2015 Feb
Approved
Mar
Apr
May
Jun
Jul
Document Tittle: Progress Update as per Revised Programme 02 Page 26 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
CSMJ2580
DI Manhole Cover & Frame
CSMJ2600
SRC 20 concrete backfill
Finish
3 26-Mar-15 A
MANHOLE: 15/1 15/1/28/10
29-Mar-15 A
Total Pocess Delays
3 26-Mar-15 A
29-Mar-15 A
-119
70 06-Jan-15 A
29-Mar-15 A
-112
Preparing shaft for MH construction
2 06-Jan-15 A
07-Jan-15 A
-65
CSMJ2620
Blinding
2 27-Jan-15 A
28-Jan-15 A
-82
CSMJ2630
Reinforcement, shuttering, concreting
4 31-Jan-15 A
03-Feb-15 A
-83
CSMJ2640
Pipe connection to manhole & pre-testing of section
2 04-Feb-15 A
05-Feb-15 A
-83
CSMJ26400
Benching work
2 07-Feb-15 A
08-Feb-15 A
-83
CSMJ2650
Bitumen primer
1 09-Feb-15 A
09-Feb-15 A
-83
CSMJ2660
Tanking membrane
1 10-Feb-15 A
10-Feb-15 A
-83
CSMJ2670
Epoxy mortor & sealant
1 11-Feb-15 A
11-Feb-15 A
-83
CSMJ2680
GRP accessories
1 25-Feb-15 A
25-Feb-15 A
-93
CSMJ2700
Backfilling
6 22-Feb-15 A
28-Feb-15 A
-88
CSMJ2690
DI Manhole Cover & Frame
3 26-Mar-15 A
29-Mar-15 A
-118
CSMJ2710
SRC 20 concrete backfill
3 26-Mar-15 A
29-Mar-15 A
-112
33 13-Jan-15 A
21-Feb-15 A
-72
CSMJ2720
Preparing shaft for MH construction
2 13-Jan-15 A
14-Jan-15 A
-62
CSMJ2730
Blinding
2 27-Jan-15 A
28-Jan-15 A
-73
CSMJ2750
Pipe connection to manhole & pre-testing of section
2 31-Jan-15 A
01-Feb-15 A
-70
CSMJ2740
Reinforcement, shuttering, concreting
5 28-Jan-15 A
02-Feb-15 A
-73
CSMJ27500
Benching work
2 02-Feb-15 A
03-Feb-15 A
-70
CSMJ2760
Bitumen primer
1 04-Feb-15 A
04-Feb-15 A
-70
CSMJ2770
Tanking membrane
1 05-Feb-15 A
05-Feb-15 A
-70
CSMJ2780
Epoxy mortor & sealant
1 07-Feb-15 A
07-Feb-15 A
-70
CSMJ2790
GRP accessories
1 08-Feb-15 A
08-Feb-15 A
-70
CSMJ2800
DI Manhole Cover & Frame
2 09-Feb-15 A
10-Feb-15 A
-70
CSMJ2810
Backfilling
5 11-Feb-15 A
17-Feb-15 A
-70
CSMJ2820
SRC 20 concrete backfill
MANHOLE: 15/1 15/1/28/12 CSMJ2830
Beaking MH and Pipe connection
REINSTATEMENT ASPHALT
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
2 19-Feb-15 A
21-Feb-15 A
-72
3 16-Mar-15 A
18-Mar-15 A
-109 -109
3 16-Mar-15 A
18-Mar-15 A
11 16-Mar-15 A
28-Mar-15 A
-85
3 25-Mar-15 A
28-Mar-15 A
-89
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
-125
CSMJ2610
MANHOLE: 15/1 15/1/28/11
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 27 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
CSMTR1360
90mm Base course
CSMTR1370
70mm Wearing course
Finish
3 25-Mar-15 A
PAVING/ CONCRETE PAVING PAVING/CONCR
28-Mar-15 A
Total Pocess Delays
3 25-Mar-15 A
28-Mar-15 A
-89
2 16-Mar-15 A
17-Mar-15 A
-76
Formation preparation
2 16-Mar-15 A
17-Mar-15 A
-77
CSMTR1420
Paving interlock
2 16-Mar-15 A
17-Mar-15 A
-76 -76
1 16-Mar-15 A
16-Mar-15 A
CSMTR1380
Excavation & concrete foundation for kerbs
1 16-Mar-15 A
16-Mar-15 A
-78
CSMTR1400
Backing concrete
1 16-Mar-15 A
16-Mar-15 A
-76
CSMTR1390
Kerbs installation
PLANT AND GR GRASS
1 16-Mar-15 A
16-Mar-15 A
-77
2 16-Mar-15 A
17-Mar-15 A
-76
CSMTR1430
Excavation for plants
2 16-Mar-15 A
17-Mar-15 A
-76
CSMTR1440
Planting/grass
2 16-Mar-15 A
17-Mar-15 A
-76
162 08-Jan-15 A
18-Jun-15 A
-184
159 11-Jan-15 A
18-Jun-15 A
-184
144 11-Jan-15 A
03-Jun-15 A
-170
54 11-Jan-15 A
15-Mar-15 A
-87 -37
HOUSE CONNECT CONNECTION SEWER IN TRENCH TREN (AREA) HOUSE CONNE CONNECTION PHASE 1 SURVEY AND D DEMOLISH CHG1000
Plot survey
2 11-Jan-15 A
12-Jan-15 A
CHG1010
Demolition of ext. underground structures
3 12-Mar-15 A
15-Mar-15 A
-87
67 24-Feb-15 A
01-May-15 A
-242 -232
PIPE WORK WORK IN IN TRENCH-HC 01 CSHCP1010
Excavation & disposal of materials
43 24-Feb-15 A
07-Apr-15 A
CSHCP1020
Bedding preparation prior to pipe laying
43 26-Feb-15 A
09-Apr-15 A
-231
CSHCP1030
Laying pipe & connecting to new manhole
42 28-Feb-15 A
10-Apr-15 A
-228
CSHCP1040
Granular & concrete surrounds
44 28-Feb-15 A
12-Apr-15 A
-227
CSHCP1050
Backfilling
46 28-Feb-15 A
14-Apr-15 A
-227
CSHCP1060
Concrete backfill
-242
PIPE WORK WORK IN IN TRENCH-HC 02
63 28-Feb-15 A
01-May-15 A
70 28-Feb-15 A
08-May-15 A 29-Mar-15 A
CSHCP1070
Excavation & disposal of materials
30 28-Feb-15 A
CSHCP1080
Bedding preparation prior to pipe laying
43 28-Feb-15 A
11-Apr-15 A
CSHCP1090
Laying pipe & connecting to new manhole
50 28-Feb-15 A
18-Apr-15 A
CSHCP1100
Granular & concrete surrounds
52 28-Feb-15 A
20-Apr-15 A
CSHCP1110
Backfilling
54 28-Feb-15 A
22-Apr-15 A
CSHCP1120
Concrete backfill
70 28-Feb-15 A
08-May-15 A
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
SI-2
2015 Feb
Mar
Apr
May
Jun
Jul
-91
CSMTR1410
KERBSTONE
Total Float SI-1
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 28 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
PIPE WORK WORK IN IN TRENCH-HC 03
Finish
98 24-Feb-15 A
01-Jun-15 A
Total Pocess Delays
CSHCP1130
Excavation & disposal of materials
86 24-Feb-15 A
22-May-15 A
CSHCP1140
Bedding preparation prior to pipe laying
84 26-Feb-15 A
24-May-15 A
Ps
CSHCP1150
Laying pipe & connecting to new manhole
84 26-Feb-15 A
26-May-15 A
Ps
CSHCP1160
Granular & concrete surrounds
84 26-Feb-15 A
28-May-15 A
Ps
CSHCP1170
Backfilling
50 07-Apr-15 A
30-May-15 A
Ps
CSHCP1180
Concrete backfill
99 25-Feb-15 A
03-Jun-15 A 13-Apr-15 A
CSHCP1190
Excavation & disposal of materials
48 25-Feb-15 A
CSHCP1200
Bedding preparation prior to pipe laying
49 26-Feb-15 A
15-Apr-15 A
CSHCP1210
Laying pipe & connecting to new manhole
51 26-Feb-15 A
17-Apr-15 A
CSHCP1220
Granular & concrete surrounds
53 26-Feb-15 A
19-Apr-15 A
CSHCP1230
Backfilling
53 28-Feb-15 A
21-Apr-15 A
CSHCP1240
Concrete backfill
INSPECTION CHAMBER INSPECTION C 1
2 02-Jun-15 A
03-Jun-15 A
21 14-Apr-15 A
04-May-15 A
1 14-Apr-15 A
14-Apr-15 A
-133
Blinding
1 15-Apr-15 A
15-Apr-15 A
-133
CHCC1030
Reinforcement, shuttering, concreting
1 16-Apr-15 A
16-Apr-15 A
-132
CHCC1040
Pipe connection to manhole & pre-testing of section
1 17-Apr-15 A
17-Apr-15 A
-132
CHCC10400
Benching work
1 18-Apr-15 A
18-Apr-15 A
-130
CHCC1050
Bitumen primer
1 19-Apr-15 A
19-Apr-15 A
-130
CHCC1060
Tanking membrane
1 20-Apr-15 A
20-Apr-15 A
-130
CHCC1070
Epoxy mortor & sealant
1 21-Apr-15 A
21-Apr-15 A
-130
CHCC1080
GRP accessories
1 22-Apr-15 A
22-Apr-15 A
-130
CHCC1090
DI Manhole Cover & Frame
1 03-May-15 A 03-May-15 A
-139
CHCC1100
Backfilling
1 04-May-15 A 04-May-15 A
-139
44 15-Apr-15 A
28-May-15 A
CHCC1120
Excavation & disposal of materials
1 15-Apr-15 A
15-Apr-15 A
-134
CHCC1130
Blinding
1 16-Apr-15 A
16-Apr-15 A
-134
CHCC1140
Reinforcement, shuttering, concreting
1 17-Apr-15 A
17-Apr-15 A
-133
CHCC1150
Pipe connection to manhole & pre-testing of section
1 18-Apr-15 A
18-Apr-15 A
-133
CHCC11500
Benching work
1 03-May-15 A 03-May-15 A
-145
Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Apr
May
Jun
Jul
Ps
Excavation & disposal of materials
Remaining Level of Effort
Mar
-139
CHCC1020
Actual Level of Effort
2015 Feb
Ps
CHCC1010
INSPECTION CHAMBER INSPECTION C 2
SI-2
Ps
2 31-May-15 A 01-Jun-15 A
PIPE WORK WORK IN IN TRENCH-HC 04
Total Float SI-1
-163
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 29 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
1 23-May-15 A 23-May-15 A
Total Pocess Delays
CHCC1160
Bitumen primer
CHCC1170
Tanking membrane
1 24-May-15 A 24-May-15 A
-164 Ps
CHCC1180
Epoxy mortor & sealant
1 25-May-15 A 25-May-15 A
-164 Ps
CHCC1190
GRP accessories
1 26-May-15 A 26-May-15 A
-164 Ps
CHCC1200
DI Manhole Cover & Frame
1 27-May-15 A 27-May-15 A
-163 Ps
CHCC1210
Backfilling
1 28-May-15 A 28-May-15 A
-163 Ps
CHCC11510
Excavation & disposal of materials
1 03-May-15 A 03-May-15 A
CHCC11520
Blinding
1 04-May-15 A
CHCC11530
Reinforcement, shuttering, concreting
1 05-May-15 A 05-May-15 A
CHCC11540
Pipe connection to manhole & pre-testing of section
1 06-May-15 A 06-May-15 A
CHCC11550
Benching work
1 07-May-15 A 07-May-15 A
CHCC11560
Bitumen primer
1 08-May-15 A 08-May-15 A
CHCC11570
Tanking membrane
1 09-May-15 A 09-May-15 A
CHCC11580
Epoxy mortor & sealant
1 10-May-15 A 10-May-15 A
CHCC11590
GRP accessories
1 11-May-15 A
CHCC11600
DI Manhole Cover & Frame
1 12-May-15 A 12-May-15 A
CHCC11610
Backfilling
Apr
May
Jun
Jul
-164 Ps
11-May-15 A
14-May-15 A
Excavation & disposal of materials
1 17-Apr-15 A
17-Apr-15 A
CHCC11630
Blinding
1 18-Apr-15 A
18-Apr-15 A
CHCC11640
Reinforcement, shuttering, concreting
1 04-May-15 A 04-May-15 A
CHCC11650
Pipe connection to manhole & pre-testing of section
1 05-May-15 A 05-May-15 A
CHCC11660
Benching work
1 06-May-15 A 06-May-15 A
CHCC11670
Bitumen primer
1 07-May-15 A 07-May-15 A
CHCC11680
Tanking membrane
1 08-May-15 A 08-May-15 A
CHCC11690
Epoxy mortor & sealant
1 09-May-15 A 09-May-15 A
CHCC11700
GRP accessories
1 10-May-15 A 10-May-15 A
CHCC11710
DI Manhole Cover & Frame
1 11-May-15 A
CHCC11720
Backfilling
1 14-May-15 A 14-May-15 A
REINSTATEMENT FOR CHAMBERS REINSTATEME
Primary Baseline
Mar
04-May-15 A
CHCC11620
Reinstatement around constructed chamber
Remaining Level of Effort
2015 Feb
1 13-May-15 A 13-May-15 A 28 17-Apr-15 A
INSPECTION CHAMBER INSPECTION C 4
Actual Level of Effort
SI-2
11 03-May-15 A 13-May-15 A
INSPECTION CHAMBER INSPECTION C 3
CHCC1220
Total Float SI-1
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
11-May-15 A
1 31-May-15 A 31-May-15 A
-165
1 31-May-15 A 31-May-15 A
-165
Checked
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 30 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
HOUSE CONNE CONNECTION PHASE 2 SURVEY AND D DEMOLISH
Finish
128 21-Jan-15 A
28-May-15 A
125 21-Jan-15 A
25-May-15 A
C.HC.P221000
Plot survey
3 21-Jan-15 A
C.HC.P221010
Demolition of ext. underground structures
3 23-May-15 A 25-May-15 A 94 24-Feb-15 A
28-May-15 A
Excavation & disposal of materials
75 24-Feb-15 A
09-May-15 A
CSHCP1260
Bedding preparation prior to pipe laying
76 25-Feb-15 A
11-May-15 A
CSHCP1270
Laying pipe & connecting to new manhole
79 24-Feb-15 A
13-May-15 A
CSHCP1280
Granular & concrete surrounds
81 24-Feb-15 A
15-May-15 A
CSHCP1290
Backfilling
82 25-Feb-15 A
17-May-15 A
CSHCP1300
Concrete backfill
93 25-Feb-15 A
28-May-15 A
INSPECTION CHAMBER INSPECTION C 5
0
REINSTATEMENT FOR CHAMBERS REINSTATEME
2 25-May-15 A
C.HC.P221020
Reinstatement around constructed chamber
Total Float SI-1
SI-2
SURVEY AND D DEMOLISH
148 22-Jan-15 A
18-Jun-15 A
-184
108 22-Jan-15 A
09-May-15 A
-157
24-Jan-15 A
Plot survey
2 22-Jan-15 A
Demolition of ext. underground structures
3 07-May-15 A 09-May-15 A 13 26-May-15 A 07-Jun-15 A
PIPE WORK WORK IN IN TRENCH-HC 06
-177
5 26-May-15 A 30-May-15 A
CSTH1020
Bedding preparation prior to pipe laying
2 31-May-15 A 01-Jun-15 A
-182
CSTH1030
Laying pipe & connecting to new manhole
4 02-Jun-15 A
05-Jun-15 A
-182
CSTH1050
Backfilling
2 06-Jun-15 A
07-Jun-15 A
-179
CSTH1060
Concrete backfill
2 06-Jun-15 A
07-Jun-15 A
-177
CSTH1040
Granular & concrete surrounds
2 06-Jun-15 A
07-Jun-15 A
-183
-181
11 31-May-15 A 10-Jun-15 A
PIPE WORK WORK IN IN TRENCH-HC 07 (SI 2) CSTH12410
Excavation & disposal of materials
5 31-May-15 A 04-Jun-15 A
CSTH12420
Bedding preparation prior to pipe laying
2 05-Jun-15 A
06-Jun-15 A
SI-2
CSTH12430
Laying pipe & connecting to new manhole
2 07-Jun-15 A
08-Jun-15 A
SI-2
CSTH12440
Granular & concrete surrounds
2 07-Jun-15 A
08-Jun-15 A
SI-2
CSTH12460
Concrete backfill
2 09-Jun-15 A
10-Jun-15 A
SI-2
CSTH12450
Backfilling
2 09-Jun-15 A
10-Jun-15 A
SI-2
Remaining W ork
Jul
-45
Excavation & disposal of materials
Primary Baseline
Jun
-155
CSTH1010
Second Baseline
May
0
CSTH1080
Actual Work
Apr
26-May-15 A
CSTH1070
Remaining Level of Effort
Mar
2 25-May-15 A 26-May-15 A
HOUSE CONNE CONNECTION PHASE 3
Actual Level of Effort
2015 Feb
24-Jan-15 A
CSHCP1250
PIPE WORK WORK IN IN TRENCH-HC 05
Total Pocess Delays
Criti... Mile...
Date
Revision
Checked
SI-2
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 31 of 35 Data Date: 22-Jun-15
Aug
Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Activity ID
Activity Name
Original Start Duration
Finish
13 05-Jun-15 A
INSPECTION CHAMBER INSPECTION C 1 (SI 2)
17-Jun-15 A
Total Pocess Delays
Total Float SI-1
SI-2
Excavation & disposal of materials
1 05-Jun-15 A
05-Jun-15 A
-183
SI-2
CSTH1110
Blinding
1 06-Jun-15 A
06-Jun-15 A
-183
SI-2
CSTH1120
Reinforcement, shuttering, concreting
2 07-Jun-15 A
08-Jun-15 A
-182
SI-2
CSTH1130
Pipe connection to manhole & pre-testing of section
1 09-Jun-15 A
09-Jun-15 A
-182
SI-2
CSTH11300
Benching work
2 10-Jun-15 A
11-Jun-15 A
-182
SI-2
CSTH1140
Bitumen primer
1 12-Jun-15 A
12-Jun-15 A
-182
SI-2
CSTH1150
Tanking membrane
1 13-Jun-15 A
13-Jun-15 A
-182
SI-2
CSTH1160
Epoxy mortor & sealant
1 14-Jun-15 A
14-Jun-15 A
-181
SI-2
CSTH1170
GRP accessories
1 15-Jun-15 A
15-Jun-15 A
-181
SI-2
CSTH1180
DI Manhole Cover & Frame
1 16-Jun-15 A
16-Jun-15 A
-181
SI-2
CSTH1190
Backfilling
1 17-Jun-15 A
17-Jun-15 A
-181
SI-2
-182
13 06-Jun-15 A
18-Jun-15 A
CSTH1210
Excavation & disposal of materials
1 06-Jun-15 A
06-Jun-15 A
-184
SI-2
CSTH1220
Blinding
1 07-Jun-15 A
07-Jun-15 A
-184
SI-2
CSTH1230
Reinforcement, shuttering, concreting
2 08-Jun-15 A
09-Jun-15 A
-183
SI-2
CSTH1240
Pipe connection to manhole & pre-testing of section
1 10-Jun-15 A
10-Jun-15 A
-183
SI-2
CSTH12400
Benching work
2 11-Jun-15 A
12-Jun-15 A
-183
SI-2
CSTH1250
Bitumen primer
1 13-Jun-15 A
13-Jun-15 A
-183
SI-2
CSTH1260
Tanking membrane
1 14-Jun-15 A
14-Jun-15 A
-183
SI-2
CSTH1270
Epoxy mortor & sealant
1 15-Jun-15 A
15-Jun-15 A
-182
SI-2
CSTH1280
GRP accessories
1 16-Jun-15 A
16-Jun-15 A
-182
SI-2
CSTH1290
DI Manhole Cover & Frame
1 17-Jun-15 A
17-Jun-15 A
-182
SI-2
CSTH1300
Backfilling
1 18-Jun-15 A
18-Jun-15 A
-182
SI-2
5 14-Jun-15 A
18-Jun-15 A
-182
5 14-Jun-15 A
18-Jun-15 A
-182
141 08-Jan-15 A
28-May-15 A
-163
141 08-Jan-15 A
28-May-15 A
-163
97 08-Jan-15 A
14-Apr-15 A
-132
REINSTATEMENT FOR CHAMBERS (SI 2) REINSTATEME CSTH1310
Reinstatement around constructed chamber
SEWER IN MICT MICTROTUNNEL HOUSE CONNE CONNECTION PHASE 2 SURVEY AND D DEMOLISH CSMTHC1390
Plot survey
2 08-Jan-15 A
10-Jan-15 A
-33
CSMTHC1400
Demolition of ext. underground structures
3 12-Apr-15 A
14-Apr-15 A
-130
88 22-Feb-15 A
22-May-15 A
-158
PIPE WORK WORK IN IN TRENCH-HC 12/13
Remaining Level of Effort Actual Level of Effort Primary Baseline
Second Baseline Actual Work Remaining W ork
Criti... Mile...
Date
Revision
Checked
Mar
Apr
May
Jun
Jul
-181
CSTH1100
INSPECTION CHAMBER INSPECTION C 2 (SI 2)
2015 Feb
SI-2
Approved
Document Tittle: Progress Update as per Revised Programme 02 Page 32 of 35 Data Date: 22-Jun-15
Aug