Total Delay Anylis

Descripción: Delay Analysis

   EMBED


Share

Transcript

Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Star t Duration ENSDSA1000 Shop drawing submit tal ENSDSA1010 Shop drawing approval PROCUREMENT MATERIAL SUBMITTAL SUBMI Finish 30 29-Jun-14 A 31-Jul-14 A 21 03-Aug-14 A Total Pocess Delays Total Float SI- 1 31-Aug-14 A -12 280 25-May-14 A 28-Feb-15 A -81 55 25-May-14 A 18-Jul-14 A -41 Readymix concrete 7 25-May-14 A 31 3 1-May-14 A 0 EMS1010 St eel reinforcement 7 25-May-14 A 31 3 1-May-14 A 0 EMS10100 Pipe bedding 7 25-May-14 A 31 31-May-14 A 0 EMS1070 Epoxy Products 7 01-Jun-14 A 07-Jun-14 A 0 EMS1080 Tanking 7 01-Jun-14 A 07 07-Jun-14 A 0 EMS1090 Bitumen Primer 7 01-Jun-14 A 07-Jun-14 A 0 EMS1120 DI Manhole Cover & Frame 7 01-Jun-14 A 07-Jun-14 A 0 EMS1130 Surface Box 7 01-Jun-14 A 07-Jun-14 A 0 EMS10600 Marker/ warning tape 7 01-Jun-14 A 07-Jun-14 A 0 EMS1100 6mm Plywood 7 01-Jun-14 A 07-Jun-14 A 0 EMS1040 VC Pipe & Fitt ings 7 12-Jul-14 A 18-Jul-14 A -48 SI -1 EMS1050 GRP Lined RC Jacking Pipes 7 12-Jul-14 A 18-Jul-14 A -48 SI -1 EMS1060 GRP Products SI -1 7 12-Jul-14 A 18-Jul-14 A -48 56 01-Jun-14 A 20-Aug-14 A -30 EMA1000 Readymix concrete 21 01-Jun-14 A 29-Jun-14 A 0 EMA1010 St eel reinforcement 21 01-Jun-14 A 29-Jun-14 A 0 EMA10100 Pipe bedding 21 01-Jun-14 A 29-Jun-14 A 0 EMA1070 Epoxy Products 21 08-Jun-14 A 06-Jul-14 A 0 EMA1080 Tanking 21 08-Jun-14 A 06 06-Jul-14 A 0 EMA1090 Bitumen Primer 21 08-Jun-14 A 06-Jul-14 A 0 EMA1100 6mm Plywood 21 08-Jun-14 A 06-Jul-14 A 0 EMA1120 DI Manhole Cover & Frame 21 08-Jun-14 A 06-Jul-14 A 0 EMA1130 Surface Box 21 08-Jun-14 A 06-Jul-14 A 0 EMA10600 Marker/ warning tape 21 08-Jun-14 A 06-Jul-14 A EMA1050 GRP Lined RC Jacking Pipes 21 20-Jul-14 A 20-Aug-14 A -35 SI -1 EMA1060 GRP Products 21 20-Jul-14 A 20-Aug-14 A -35 SI -1 EMA1040 VC Pipe & Fitt ings SI -1 PROCURE MATER MATERIAL Remaining Level of Effort  Actual Level of Effort Effort Primary Baseline Second Baseline Criti...  Actual Work Mile... Remaining ng W ork Date Rev ision Mar Apr May Jun Jul 0 21 20-Jul-14 A 20-Aug-14 A -35 63 30-Jun-14 A 03-Sep-14 A -42 Checked 2015 Feb -18 EMS1000 MATERIAL APPROVAL APPR SI-2 Approv ed Document Tittle: Progress Update as per Revised Programme 02 Page 3 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish Total Pocess Delays PMP1000 Readymix concrete 14 30-Jun-14 A 13-Jul-14 A 0 PMP1010 Steel reinforcement & Formwork 14 30-Jun-14 A 13-Jul-14 A 0 PMP10100 Pipe bedding 14 30-Jun-14 A 13-Jul-14 A 0 PMP1070 Epoxy Products 14 07-Jul-14 A 20-Jul-14 A 0 PMP1080 Tanking 14 07-Jul-14 A 20-Jul-14 A 0 PMP1090 Bitumen Primer 14 07-Jul-14 A 20-Jul-14 A 0 PMP1100 6mm Plywood 14 07-Jul-14 A 20-Jul-14 A 0 PMP1120 DI Manhole Cover & Frame 14 07-Jul-14 A 20-Jul-14 A 0 PMP1130 Surface Box 14 07-Jul-14 A 20-Jul-14 A 0 20-Jul-14 A Total Float SI-1 Marker/warning tape 14 07-Jul-14 A PMP1040 VC Pipe & Fittings 14 21-Aug-14 A 03-Sep-14 A -49 SI-1 PMP1060 GRP Products 14 21-Aug-14 A -49 SI-1 PMP1050 GRP Lined RC Jacking Pipes 14 21-Aug-14 A MATERIAL DELIVERY DELIV TO SITE 03-Sep-14 A -49 236 30-Jun-14 A 28-Feb-15 A -79 Readymix concrete 157 30-Jun-14 A 09-Dec-14 A 0 PMD1050 GRP Lined RC Jacking Pipes 141 21-Aug-14 A 12-Jan-15 A -50 PMD1010 Steel reinforcement 236 30-Jun-14 A 28-Feb-15 A -86 PMD1040 VC Pipe & Fittings 187 21-Aug-14 A 28-Feb-15 A -91 SI-1 PMD1060 GRP Products 187 21-Aug-14 A 28-Feb-15 A -124 SI-1 PMD1070 Epoxy Products 229 07-Jul-14 A 28-Feb-15 A -204 PMD1080 Tanking 229 07-Jul-14 A 28-Feb-15 A -128 PMD1090 Bitumen Primer 229 07-Jul-14 A 28-Feb-15 A -175 PMD1100 6mm Plywood 229 07-Jul-14 A 28-Feb-15 A -182 PMD10100 Pipe bedding 236 30-Jun-14 A 28-Feb-15 A -222 PMD1120 DI Manhole Cover & Frame 229 07-Jul-14 A 28-Feb-15 A -215 PMD1130 Surface Box 229 07-Jul-14 A 28-Feb-15 A -215 PMD10600 Marker/warning tape 229 07-Jul-14 A 28-Feb-15 A -124 359 29-Jun-14 A 22-Jun-15 A -184 359 29-Jun-14 A 22-Jun-15 A -196 287 29-Jun-14 A 11-Apr-15 A -216 283 29-Jun-14 A 07-Apr-15 A -238 219 29-Jun-14 A 19-Mar-15 A -198 SEWER IN TRENCH TRENC PHASE 1: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 VC PIP PIPE E WORK WORKS: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 200mm NOMINAL NOMIN BORE 33.88m: From MH 15/1/28/12/6 to MH 15/1/28/12/5 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul 0 PMD1000 CONSTRUCTION 2015 Feb PMP10600 03-Sep-14 A SI-2 SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 4 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish 4 22-Nov-14 A CST1220 Excavation & disposal of materials CST1230 Bedding preparation prior to VC pipe laying 3 27-Nov-14 A 30-Nov-14 A -101 CST1240 Laying VC pipes & fittings and pre-testing 2 04-Dec-14 A 06-Dec-14 A -104 CST1250 Granular & concrete surrounds 2 09-Dec-14 A 10-Dec-14 A -106 CST1260 Backfilling 4 10-Dec-14 A 14-Dec-14 A -106 CST1270 SRC 20 concrete backfill 2 17-Dec-14 A 20-Dec-14 A -108 CST1350 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A -183 88 10-Jan-15 A 07-Apr-15 A -238 -180 300mm NOMINAL NOMIN BORE 59.46m: From MH 15/1/28/12/1 to MH 15/1/28/12 25-Nov-14 A Total Pocess Delays Recovery 0 10-Jan-15 A CST1290 Excavation & disposal of materials 2 01-Mar-15 A 02-Mar-15 A 75 10-Jan-15 A 25-Mar-15 A Delay: Issuance of Excavation permit CST1300 Bedding preparation prior to VC pipe laying 4 28-Mar-15 A 31-Mar-15 A -203 CST1310 Laying VC pipes & fittings and pre-testing 5 28-Mar-15 A 01-Apr-15 A -202 CST1320 Granular & concrete surrounds 6 28-Mar-15 A 02-Apr-15 A -201 CST1330 Backfilling 7 28-Mar-15 A 04-Apr-15 A -199 CST1340 SRC 20 concrete backfill 8 29-Mar-15 A 06-Apr-15 A -199 CST1420 Marker tape installation 1 07-Apr-15 A 07-Apr-15 A -199 46 16-Feb-15 A 09-Apr-15 A 46 16-Feb-15 A 09-Apr-15 A 1 16-Mar-15 A 16-Mar-15 A 05-Apr-15 A CST2330 SRC 20 concrete backfill CST2280 Excavation & disposal of materials 42 16-Feb-15 A CST2290 Bedding preparation prior to VC pipe laying 40 18-Feb-15 A 05-Apr-15 A CST2300 Laying VC pipes & fittings and pre-testing 39 19-Feb-15 A 05-Apr-15 A CST2310 Granular & concrete surrounds 38 21-Feb-15 A 05-Apr-15 A CST2320 Backfilling 38 22-Feb-15 A 06-Apr-15 A CST2340 Marker tape installation 2 08-Apr-15 A MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/12/6 29-Mar-15 A -178 25 26-Jul-14 A 26-Aug-14 A -14 Excavation & disposal of materials 4 26-Jul-14 A 02-Aug-14 A -14 CSTM1020 Blinding 1 03-Aug-14 A 03-Aug-14 A -14 CSTM1030 Reinforcement, shuttering, concreting 4 04-Aug-14 A 07-Aug-14 A -14 CSTM1040 Pipe connection to manhole & pre-testing of section 2 09-Aug-14 A 10-Aug-14 A -14 Remaining Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul 09-Apr-15 A 204 26-Jul-14 A CSTM1010  Actual Level of Effort 2015 Feb -99 CST129.10 FC-01 SI-2 ery CST129 FUTURE CONNE CONNECTION Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 6 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish Total Pocess Delays CSTM10400 Benching work 2 11-Aug-14 A 12-Aug-14 A -14 CSTM1050 Bitumen primer 1 13-Aug-14 A 13-Aug-14 A -14 CSTM1060 Tanking membrane 1 14-Aug-14 A 14-Aug-14 A -14 CSTM1070 Epoxy mortor & sealant 2 16-Aug-14 A 17-Aug-14 A -14 CSTM1080 GRP accessories 2 18-Aug-14 A 19-Aug-14 A -14 CSTM1090 DI Manhole Cover & Frame 2 20-Aug-14 A 21-Aug-14 A -14 CSTM1100 Backfilling 3 23-Aug-14 A 25-Aug-14 A -14 CSTM1330 SRC 20 concrete backfill 1 26-Aug-14 A 26-Aug-14 A -14 25 03-Aug-14 A 31-Aug-14 A MANHOLE: 15/1 15/1/28/12/5 CSTM28210 Excavation & disposal of materials 4 03-Aug-14 A 06-Aug-14 A CSTM28220 Blinding 1 07-Aug-14 A 07-Aug-14 A CSTM28230 Reinforcement, shuttering, concreting 4 09-Aug-14 A 12-Aug-14 A CSTM28240 Pipe connection to manhole & pre-testing of section 2 13-Aug-14 A 14-Aug-14 A CSTM28250 Benching work 2 16-Aug-14 A 17-Aug-14 A CSTM28260 Bitumen primer 1 18-Aug-14 A 18-Aug-14 A CSTM28270 Tanking membrane 1 19-Aug-14 A 19-Aug-14 A CSTM28280 Epoxy mortor & sealant 2 20-Aug-14 A 21-Aug-14 A CSTM28290 GRP accessories 2 23-Aug-14 A 24-Aug-14 A CSTM28300 DI Manhole Cover & Frame 2 25-Aug-14 A 26-Aug-14 A CSTM28310 Backfilling 3 27-Aug-14 A 30-Aug-14 A CSTM28320 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/12/4 1 31-Aug-14 A 31-Aug-14 A 24 21-Aug-14 A 17-Sep-14 A Excavation & disposal of materials 4 21-Aug-14 A 25-Aug-14 A -34 CSTM1360 Blinding 1 26-Aug-14 A 26-Aug-14 A -34 CSTM1370 Reinforcement, shuttering, concreting 4 27-Aug-14 A 31-Aug-14 A -34 CSTM1380 Pipe connection to manhole & pre-testing of section 2 01-Sep-14 A 02-Sep-14 A -32 CSTM13800 Benching work 2 03-Sep-14 A 04-Sep-14 A -32 CSTM1390 Bitumen primer 1 06-Sep-14 A 06-Sep-14 A -32 CSTM1400 Tanking membrane 1 07-Sep-14 A 07-Sep-14 A -32 CSTM1410 Epoxy mortor & sealant 1 08-Sep-14 A 08-Sep-14 A -32 CSTM1420 GRP accessories 2 09-Sep-14 A 10-Sep-14 A -32 CSTM1430 DI Manhole Cover & Frame 2 11-Sep-14 A 13-Sep-14 A -32 Remaining Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked SI-2 2015 Feb Mar Apr May Jun Jul -32 CSTM1350  Actual Level of Effort Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 7 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration CSTM1440 Backfilling CSTM1450 SRC 20 concrete backfill Finish 3 14-Sep-14 A 16-Sep-14 A MANHOLE: 15/1 15/1/28/12/3 Total Pocess Delays 1 17-Sep-14 A 17-Sep-14 A -32 32 17-Aug-14 A 22-Sep-14 A -32 Excavation & disposal of materials 4 17-Aug-14 A 20-Aug-14 A -25 CSTM1480 Blinding 1 28-Aug-14 A 28-Aug-14 A -31 CSTM1490 Reinforcement, shuttering, concreting 4 01-Sep-14 A 04-Sep-14 A -33 CSTM1500 Pipe connection to manhole & pre-testing of section 2 06-Sep-14 A 07-Sep-14 A -32 CSTM15000 Benching work 2 08-Sep-14 A 09-Sep-14 A -32 CSTM1510 Bitumen primer 1 10-Sep-14 A 10-Sep-14 A -32 CSTM1520 Tanking membrane 1 11-Sep-14 A 11-Sep-14 A -32 CSTM1530 Epoxy mortor & sealant 1 13-Sep-14 A 13-Sep-14 A -32 CSTM1540 GRP accessories 2 14-Sep-14 A 15-Sep-14 A -32 CSTM1550 DI Manhole Cover & Frame 2 16-Sep-14 A 17-Sep-14 A -32 CSTM1560 Backfilling 3 18-Sep-14 A 21-Sep-14 A -32 CSTM1570 SRC 20 concrete backfill 1 22-Sep-14 A 22-Sep-14 A 27 21-Dec-14 A 20-Jan-15 A SRC 20 concrete backfill 1 21-Dec-14 A 21-Dec-14 A -96 Excavation & disposal of materials 4 25-Dec-14 A 29-Dec-14 A -123 CSTM1600 Blinding 1 30-Dec-14 A 30-Dec-14 A -123 CSTM1610 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A -123 CSTM1620 Pipe connection to manhole & pre-testing of section 2 05-Jan-15 A 06-Jan-15 A -123 CSTM16200 Benching work 2 07-Jan-15 A 08-Jan-15 A -123 CSTM1630 Bitumen primer 1 10-Jan-15 A 10-Jan-15 A -123 CSTM1640 Tanking membrane 1 11-Jan-15 A 11-Jan-15 A -123 CSTM1650 Epoxy mortor & sealant 1 12-Jan-15 A 12-Jan-15 A -123 CSTM1660 GRP accessories 2 13-Jan-15 A 14-Jan-15 A -123 CSTM1670 DI Manhole Cover & Frame 2 15-Jan-15 A 17-Jan-15 A -123 CSTM1680 Backfilling 3 18-Jan-15 A 20-Jan-15 A -123 -178 81 24-Dec-14 A 29-Mar-15 A CSTM1710 Excavation & disposal of materials 4 24-Dec-14 A 28-Dec-14 A -122 CSTM1720 Blinding 2 28-Dec-14 A 29-Dec-14 A -122 CSTM1730 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A -123 Remaining Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul -32 CSTM1590  Actual Level of Effort 2015 Feb -122 CSTM1690 MANHOLE: 15/1 15/1/28/12/1 SI-2 -32 CSTM1470 MANHOLE: 15/1 15/1/28/12/2 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 8 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name CSTM1740 Original Start Duration Pipe connection to manhole & pre-testing of section Finish 3 05-Jan-15 A 07-Jan-15 A Total Pocess Delays Benching work 2 08-Jan-15 A 10-Jan-15 A -124 CSTM1750 Bitumen primer 1 13-Jan-15 A 13-Jan-15 A -126 CSTM1760 Tanking membrane 1 29-Jan-15 A 29-Jan-15 A -139 CSTM1770 Epoxy mortor & sealant 1 25-Feb-15 A 25-Feb-15 A -160 CSTM1780 GRP accessories 2 26-Feb-15 A 28-Feb-15 A -160 CSTM1800 Backfilling 4 24-Feb-15 A 28-Feb-15 A -155 CSTM1790 DI Manhole Cover & Frame 3 21-Mar-15 A 23-Mar-15 A -178 CSTM1810 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -178 79 25-Dec-14 A 28-Mar-15 A CSTM28330 Excavation & disposal of materials 5 25-Dec-14 A 30-Dec-14 A CSTM28340 Blinding 1 01-Jan-15 A 01-Jan-15 A CSTM28350 Reinforcement, shuttering, concreting 4 03-Jan-15 A 06-Jan-15 A CSTM28360 Pipe connection to manhole & pre-testing of section 2 07-Jan-15 A 08-Jan-15 A CSTM28370 Benching work 2 10-Jan-15 A 11-Jan-15 A CSTM28380 Bitumen primer 1 12-Jan-15 A 12-Jan-15 A CSTM28390 Tanking membrane 1 13-Jan-15 A 13-Jan-15 A CSTM28400 Epoxy mortor & sealant 2 19-Mar-15 A 21-Mar-15 A CSTM28410 GRP accessories 3 21-Mar-15 A 23-Mar-15 A CSTM28420 DI Manhole Cover & Frame 3 23-Mar-15 A 25-Mar-15 A CSTM28430 Backfilling 4 24-Mar-15 A 28-Mar-15 A CSTM28440 SRC 20 concrete backfill REINSTATEMENT ASPHALT 2 26-Mar-15 A 28-Mar-15 A 41 23-Feb-15 A 11-Apr-15 A -180 39 23-Feb-15 A 08-Apr-15 A -182 -186 CSTR1110 90mm Base course 38 23-Feb-15 A 07-Apr-15 A CSTR1120 70mm Wearing course 27 09-Mar-15 A 08-Apr-15 A -182 18 22-Mar-15 A 11-Apr-15 A -186 KERBSTONE CSTR1130 Excavation & concrete foundation for kerbs 16 22-Mar-15 A 08-Apr-15 A -186 CSTR1140 Kerbs installation 17 22-Mar-15 A 09-Apr-15 A -186 CSTR1150 Backing concrete 18 22-Mar-15 A 11-Apr-15 A -186 2 18-Mar-15 A 19-Mar-15 A -163 2 18-Mar-15 A 19-Mar-15 A -165 PAVING/ CONCRETE PAVING PAVING/CONCR CSTR1160 Formation preparation Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked SI-2 2015 Feb Mar Apr May Jun Jul -124 CSTM17400 MANHOLE: 15/1 15/1/28/12 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 9 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish CST2220 Bedding preparation prior to VC pipe laying 11 11-Feb-15 A CST2230 Laying VC pipes & fittings and pre-testing 11 11-Feb-15 A 24-Feb-15 A CST2240 Granular & concrete surrounds 11 11-Feb-15 A 24-Feb-15 A CST2250 Backfilling 11 11-Feb-15 A 24-Feb-15 A CST2260 SRC 20 concrete backfill 10 14-Feb-15 A 24-Feb-15 A CST2270 Marker tape installation 300mm NOMIN NOMINAL BORE 71.5m: From MH 15/1/28/14 to MH 15/1/28/15 Total Pocess Delays 2 17-Mar-15 A 18-Mar-15 A 180 16-Aug-14 A 18-Mar-15 A -148 15 Excavation & disposal of materials 5 16-Aug-14 A 20-Aug-14 A CST1370 Bedding preparation prior to VC pipe laying 5 26-Aug-14 A 31-Aug-14 A 8 CST1380 Laying VC pipes & fittings and pre-testing 3 28-Aug-14 A 31-Aug-14 A 10 CST1390 Granular & concrete surrounds 2 31-Aug-14 A 01-Sep-14 A 11 CST1400 Backfilling 3 02-Sep-14 A 04-Sep-14 A 11 CST1410 SRC 20 concrete backfill 3 06-Sep-14 A 08-Sep-14 A 10 CST1490 Marker tape installation 2 17-Mar-15 A 18-Mar-15 A -148 153 16-Sep-14 A 18-Mar-15 A -145 CST1430 Excavation & disposal of materials 134 16-Sep-14 A 24-Feb-15 A -141 CST1440 Bedding preparation prior to VC pipe laying 130 21-Sep-14 A 24-Feb-15 A -139 CST1450 Laying VC pipes & fittings and pre-testing 131 23-Sep-14 A 28-Feb-15 A -140 CST1460 Granular & concrete surrounds 129 25-Sep-14 A 28-Feb-15 A -136 CST1470 Backfilling 127 28-Sep-14 A 28-Feb-15 A -132 CST1480 SRC 20 concrete backfill 124 01-Oct-14 A 28-Feb-15 A -130 CST1560 Marker tape installation 2 17-Mar-15 A 18-Mar-15 A -145 70 18-Feb-15 A 10-May-15 A FUTURE CONNE CONNECTION 46 18-Feb-15 A 12-Apr-15 A CST2350 Excavation & disposal of materials 14 18-Feb-15 A 05-Mar-15 A CST2360 Bedding preparation prior to VC pipe laying 12 21-Feb-15 A 06-Mar-15 A CST2370 Laying VC pipes & fittings and pre-testing 11 22-Feb-15 A 06-Mar-15 A CST2380 Granular & concrete surrounds 11 23-Feb-15 A 07-Mar-15 A CST2390 Backfilling 10 24-Feb-15 A 07-Mar-15 A CST2400 SRC 20 concrete backfill 1 09-Apr-15 A 09-Apr-15 A CST2410 Marker tape installation 2 11-Apr-15 A 12-Apr-15 A 45 21-Feb-15 A 13-Apr-15 A FC-02 FC-03 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked SI-2 2015 Feb Mar Apr May Jun Jul 24-Feb-15 A CST1360 300mm NOMINAL NOMIN BORE 60m: From MH 15/1/28/15 to MH 15/1/28/16 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 11 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish CST2420 Excavation & disposal of materials 12 21-Feb-15 A CST2430 Bedding preparation prior to VC pipe laying 11 23-Feb-15 A 07-Mar-15 A CST2440 Laying VC pipes & fittings and pre-testing 10 24-Feb-15 A 07-Mar-15 A CST2450 Granular & concrete surrounds 10 25-Feb-15 A 08-Mar-15 A CST2460 Backfilling 9 26-Feb-15 A 08-Mar-15 A CST2470 SRC 20 concrete backfill 1 11-Apr-15 A 11-Apr-15 A CST2480 Marker tape installation 1 12-Apr-15 A 13-Apr-15 A 66 23-Feb-15 A 10-May-15 A 05-Apr-15 A FC-04 Excavation & disposal of materials 36 23-Feb-15 A CST2500 Bedding preparation prior to VC pipe laying 34 25-Feb-15 A 05-Apr-15 A CST2510 Laying VC pipes & fittings and pre-testing 34 26-Feb-15 A 06-Apr-15 A CST2520 Granular & concrete surrounds 33 28-Feb-15 A 06-Apr-15 A CST2530 Backfilling 33 28-Feb-15 A 06-Apr-15 A CST2540 SRC 20 concrete backfill 24 12-Apr-15 A 09-May-15 A CST2550 Marker tape installation 24 13-Apr-15 A 10-May-15 A 29 08-Mar-15 A 09-Apr-15 A 06-Apr-15 A CST2560 Excavation & disposal of materials 26 08-Mar-15 A CST2570 Bedding preparation prior to VC pipe laying 23 11-Mar-15 A 06-Apr-15 A CST2580 Laying VC pipes & fittings and pre-testing 22 12-Mar-15 A 06-Apr-15 A CST2590 Granular & concrete surrounds 21 14-Mar-15 A 06-Apr-15 A CST2600 Backfilling 21 14-Mar-15 A 06-Apr-15 A CST2610 SRC 20 concrete backfill 21 16-Mar-15 A 08-Apr-15 A CST2620 Marker tape installation 20 18-Mar-15 A 09-Apr-15 A 98 01-Dec-14 A 26-Mar-15 A 73 03-Dec-14 A 28-Feb-15 A MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/13 CSTM28450 Excavation & disposal of materials 4 03-Dec-14 A 07-Dec-14 A CSTM28460 Blinding 2 08-Dec-14 A 09-Dec-14 A CSTM28470 Reinforcement, shuttering, concreting 5 08-Dec-14 A 13-Dec-14 A CSTM28480 Pipe connection to manhole & pre-testing of section 3 15-Dec-14 A 17-Dec-14 A CSTM28490 Benching work 3 20-Dec-14 A 22-Dec-14 A CSTM28500 Bitumen primer 2 23-Dec-14 A 24-Dec-14 A CSTM28510 Tanking membrane 1 02-Feb-15 A 02-Feb-15 A Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Total Float SI-1 SI-2 2015 Feb Mar Apr May Jun Jul 06-Mar-15 A CST2490 FC-05 Total Pocess Delays -140 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 12 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish CSTM28520 Epoxy mortor & sealant 1 03-Feb-15 A 03-Feb-15 A CSTM28530 GRP accessories 2 04-Feb-15 A 05-Feb-15 A CSTM28550 Backfilling 3 09-Feb-15 A 11-Feb-15 A CSTM28560 SRC 20 concrete backfill 2 18-Feb-15 A 19-Feb-15 A CSTM28540 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A 71 04-Dec-14 A 26-Feb-15 A MANHOLE: 15/1 15/1/28/14 CSTM28570 Excavation & disposal of materials 4 04-Dec-14 A 08-Dec-14 A CSTM28580 Blinding 2 11-Dec-14 A 13-Dec-14 A CSTM28590 Reinforcement, shuttering, concreting 4 14-Dec-14 A 17-Dec-14 A CSTM28600 Pipe connection to manhole & pre-testing of section 2 17-Dec-14 A 20-Dec-14 A CSTM28610 Benching work 3 21-Dec-14 A 23-Dec-14 A CSTM28620 Bitumen primer 2 08-Jan-15 A 10-Jan-15 A CSTM28630 Tanking membrane 2 12-Jan-15 A 13-Jan-15 A CSTM28640 Epoxy mortor & sealant 1 14-Jan-15 A 14-Jan-15 A CSTM28650 GRP accessories 2 15-Jan-15 A 17-Jan-15 A CSTM28670 Backfilling 3 04-Feb-15 A 07-Feb-15 A CSTM28680 SRC 20 concrete backfill 2 19-Feb-15 A 21-Feb-15 A CSTM28660 DI Manhole Cover & Frame 2 25-Feb-15 A 26-Feb-15 A 31 22-Jan-15 A 28-Feb-15 A MANHOLE: 15/1 15/1/28/14/1 CSTM28690 Excavation & disposal of materials 4 22-Jan-15 A 26-Jan-15 A CSTM28700 Blinding 1 02-Feb-15 A 02-Feb-15 A CSTM28710 Reinforcement, shuttering, concreting 4 03-Feb-15 A 07-Feb-15 A CSTM28720 Pipe connection to manhole & pre-testing of section 2 08-Feb-15 A 09-Feb-15 A CSTM28730 Benching work 2 10-Feb-15 A 11-Feb-15 A CSTM28740 Bitumen primer 1 14-Feb-15 A 14-Feb-15 A CSTM28750 Tanking membrane 1 15-Feb-15 A 15-Feb-15 A CSTM28760 Epoxy mortor & sealant 1 16-Feb-15 A 16-Feb-15 A CSTM28770 GRP accessories 2 17-Feb-15 A 18-Feb-15 A CSTM28790 Backfilling 3 22-Feb-15 A 24-Feb-15 A CSTM28800 SRC 20 concrete backfill 1 25-Feb-15 A 25-Feb-15 A CSTM28780 DI Manhole Cover & Frame 1 27-Feb-15 A 28-Feb-15 A 32 21-Jan-15 A 28-Feb-15 A MANHOLE: 15/1 15/1/28/14/2 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Total Pocess Delays Total Float SI-1 SI-2 2015 Feb Approved Mar Apr May Jun Jul Document Tittle: Progress Update as per Revised Programme 02 Page 13 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish CSTM28810 Excavation & disposal of materials 4 21-Jan-15 A 25-Jan-15 A CSTM28820 Blinding 1 02-Feb-15 A 02-Feb-15 A CSTM28830 Reinforcement, shuttering, concreting 4 03-Feb-15 A 07-Feb-15 A CSTM28840 Pipe connection to manhole & pre-testing of section 2 08-Feb-15 A 09-Feb-15 A CSTM28850 Benching work 2 10-Feb-15 A 11-Feb-15 A CSTM28860 Bitumen primer 1 14-Feb-15 A 14-Feb-15 A CSTM28870 Tanking membrane 1 15-Feb-15 A 15-Feb-15 A CSTM28880 Epoxy mortor & sealant 1 16-Feb-15 A 16-Feb-15 A CSTM28890 GRP accessories 2 17-Feb-15 A 18-Feb-15 A CSTM28910 Backfilling 3 22-Feb-15 A 24-Feb-15 A CSTM28920 SRC 20 concrete backfill 1 26-Feb-15 A 26-Feb-15 A CSTM28900 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A 75 01-Dec-14 A 28-Feb-15 A MANHOLE: 15/1 15/1/28/15 Total Pocess Delays Excavation & disposal of materials 4 01-Dec-14 A 04-Dec-14 A -70 CSTM1960 Blinding 2 06-Dec-14 A 07-Dec-14 A -71 CSTM1970 Reinforcement, shuttering, concreting 5 09-Dec-14 A 14-Dec-14 A -73 CSTM1980 Pipe connection to manhole & pre-testing of section 3 15-Dec-14 A 17-Dec-14 A -74 CSTM19800 Benching work 3 17-Dec-14 A 21-Dec-14 A -74 CSTM1990 Bitumen primer 2 24-Dec-14 A 25-Dec-14 A -77 CSTM2000 Tanking membrane 2 27-Dec-14 A 28-Dec-14 A -78 CSTM2010 Epoxy mortor & sealant 1 08-Feb-15 A 08-Feb-15 A -113 CSTM2020 GRP accessories 2 09-Feb-15 A 10-Feb-15 A -113 CSTM2040 Backfilling 3 15-Feb-15 A 17-Feb-15 A -113 CSTM2030 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A -125 CSTM2050 SRC 20 concrete backfill 1 28-Feb-15 A 28-Feb-15 A -121 45 02-Feb-15 A 26-Mar-15 A -140 CSTM2070 Excavation & disposal of materials 3 02-Feb-15 A 04-Feb-15 A -122 CSTM2080 Blinding 1 05-Feb-15 A 05-Feb-15 A -122 CSTM2090 Reinforcement, shuttering, concreting 4 07-Feb-15 A 10-Feb-15 A -122 CSTM2100 Pipe connection to manhole & pre-testing of section 2 11-Feb-15 A 14-Feb-15 A -118 CSTM21000 Benching work 2 15-Feb-15 A 16-Feb-15 A -118 CSTM2110 Bitumen primer 1 17-Feb-15 A 17-Feb-15 A -118 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked SI-2 2015 Feb Mar Apr May Jun Jul -121 CSTM1950 MANHOLE: 15/1 15/1/28/16 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 14 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish 1 18-Feb-15 A CSTM2120 Tanking membrane CSTM2130 Epoxy mortor & sealant 1 19-Feb-15 A 19-Feb-15 A -118 CSTM2140 GRP accessories 2 21-Feb-15 A 22-Feb-15 A -118 CSTM2160 Backfilling 3 25-Feb-15 A 28-Feb-15 A -118 CSTM2170 SRC 20 concrete backfill 3 25-Feb-15 A 28-Feb-15 A -117 CSTM2150 DI Manhole Cover & Frame 2 25-Mar-15 A 26-Mar-15 A -144 54 11-Feb-15 A 15-Apr-15 A -141 54 11-Feb-15 A 15-Apr-15 A -147 49 11-Feb-15 A 09-Apr-15 A -147 6 09-Apr-15 A 15-Apr-15 A -147 2 09-Apr-15 A 11-Apr-15 A -145 REINSTATEMENT ASPHALT CSTR1010 90mm Base course CSTR1020 70mm Wearing course KERBSTONE 18-Feb-15 A Total Pocess Delays Excavation & concrete foundation for kerbs 2 09-Apr-15 A 11-Apr-15 A -147 CSTR1040 Kerbs installation 2 09-Apr-15 A 11-Apr-15 A -146 CSTR1050 Backing concrete 2 09-Apr-15 A 11-Apr-15 A -145 3 09-Apr-15 A 12-Apr-15 A -142 CSTR1060 Formation preparation 3 09-Apr-15 A 12-Apr-15 A -144 CSTR1070 Paving interlock 3 09-Apr-15 A 12-Apr-15 A -142 -140 5 09-Apr-15 A 14-Apr-15 A CSTR1080 Excavation for plants 3 09-Apr-15 A 12-Apr-15 A -140 CSTR1090 Planting/grass 3 12-Apr-15 A 14-Apr-15 A -140 PHASE 3: FROM MH 15/1/28/17 TO 15/1/28/25 155 19-Jan-15 A 22-Jun-15 A -196 VC PIPE WORK WORKS: 15/1/28/17 TO 15/1/28/21 127 16-Feb-15 A 22-Jun-15 A -217 55 19-Feb-15 A 14-Apr-15 A -195 -137 PLANT AND GR GRASS 300mm NOMINAL NOMIN BORE 70m: From MH 15/1/28/16 to MH 15/1/28/17 CST1500 Excavation & disposal of materials 10 19-Feb-15 A 02-Mar-15 A CST1510 Bedding preparation prior to VC pipe laying 1 28-Mar-15 A 28-Mar-15 A -157 CST1520 Laying VC pipes & fittings and pre-testing 1 28-Mar-15 A 28-Mar-15 A -155 CST1530 Granular & concrete surrounds 1 28-Mar-15 A 28-Mar-15 A -153 CST1540 Backfilling 1 12-Apr-15 A 12-Apr-15 A -191 CST1550 SRC 20 concrete backfill 1 13-Apr-15 A 13-Apr-15 A -190 CST1630 Marker tape installation 1 14-Apr-15 A 14-Apr-15 A -190 39 12-Apr-15 A 30-May-15 A -198 200mm NOMIN NOMINAL BORE 45.93m: From MH 15/1/28/17 to MH 15/1/28/18 0000.30 As per Al Jazeera, TCTC shall be allowed to work Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Revision Checked 2015 Feb Mar Apr May Jun Jul Aug  As per Al Jazeera, TCTC shall be allowe 0 12-Apr-15 A Date SI-2 -118 CSTR1030 PAVING/ CONCRETE PAVING PAVING/CONCR Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 15 of 35 Data Date: 22-Jun-15 Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name CST1840 Original Start Duration Marker tape installation Finish Total Pocess Delays 2 29-Mar-15 A 30-Mar-15 A -133 27 22-Feb-15 A 24-Mar-15 A -107 CST1780 Excavation & disposal of materials 11 22-Feb-15 A 05-Mar-15 A -100 CST1790 Bedding preparation prior to VC pipe laying 11 24-Feb-15 A 08-Mar-15 A -101 CST1800 Laying VC pipes & fittings and pre-testing 1 14-Mar-15 A 14-Mar-15 A -104 CST1810 Granular & concrete surrounds 1 15-Mar-15 A 15-Mar-15 A -104 CST1820 Backfilling 1 24-Mar-15 A 24-Mar-15 A -109 CST1910 Marker tape installation 1 24-Mar-15 A 24-Mar-15 A -107 CST1830 SRC 20 concrete backfill 1 24-Mar-15 A 24-Mar-15 A -108 11 04-Apr-15 A 14-Apr-15 A 11 04-Apr-15 A 14-Apr-15 A 05-Apr-15 A 200mm NOMIN NOMINAL BORE 14.68m: From MH 15/1/28/20 to MH 15/1/28/21 FUTURE CONNE CONNECTION FC-06 CST2980 Excavation & disposal of materials 2 04-Apr-15 A CST2990 Bedding preparation prior to VC pipe laying 1 06-Apr-15 A 06-Apr-15 A CST3000 Laying VC pipes & fittings and pre-testing 1 07-Apr-15 A 07-Apr-15 A CST3010 Granular & concrete surrounds 1 09-Apr-15 A 09-Apr-15 A CST3020 Backfilling 1 11-Apr-15 A 11-Apr-15 A CST3030 SRC 20 concrete backfill 1 12-Apr-15 A 12-Apr-15 A CST3040 Marker tape installation 2 13-Apr-15 A 14-Apr-15 A 152 19-Jan-15 A 19-Jun-15 A -197 38 09-Mar-15 A 15-Apr-15 A -179 MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/17 CSTM2190 Excavation & disposal of materials 1 09-Mar-15 A 09-Mar-15 A -140 CSTM2200 Blinding 1 10-Mar-15 A 10-Mar-15 A -140 CSTM2210 Reinforcement, shuttering, concreting 1 11-Mar-15 A 11-Mar-15 A -137 CSTM2220 Pipe connection to manhole & pre-testing of section 1 12-Mar-15 A 12-Mar-15 A -136 CSTM22200 Benching work 1 12-Mar-15 A 12-Mar-15 A -134 CSTM2230 Bitumen primer 1 14-Mar-15 A 14-Mar-15 A -134 CSTM2240 Tanking membrane 1 14-Mar-15 A 14-Mar-15 A -133 CSTM2250 Epoxy mortor & sealant 1 14-Mar-15 A 14-Mar-15 A -132 CSTM2260 GRP accessories 1 12-Apr-15 A 12-Apr-15 A -181 CSTM2270 DI Manhole Cover & Frame 1 13-Apr-15 A 13-Apr-15 A -180 CSTM2280 Backfilling 1 14-Apr-15 A 14-Apr-15 A -178 CSTM2290 SRC 20 concrete backfill 1 15-Apr-15 A 15-Apr-15 A -177 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Total Float SI-1 SI-2 2015 Feb Approved Mar Apr May Jun Jul Document Tittle: Progress Update as per Revised Programme 02 Page 17 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration MANHOLE: 15/1 15/1/28/18 Finish 120 19-Jan-15 A 18-May-15 A 22-Feb-15 A Total Pocess Delays Delay: Issuance of Excavation permit 35 19-Jan-15 A 0000.20 Delay: Al Jazeera Stopped the Work 37 23-Feb-15 A 31-Mar-15 A CSTM2310 Excavation & disposal of materials 2 12-Apr-15 A 13-Apr-15 A CSTM2320 Blinding/Tanking & Screeding 3 14-Apr-15 A 16-Apr-15 A CSTM2330 Reinforcement, shuttering, concreting (Base & Wall) 4 01-May-15 A 04-May-15 A CSTM2340 Pipe connection to manhole & Backdrob 4 05-May-15 A 08-May-15 A -178 CSTM23400 Bitumen primer 1 09-May-15 A 09-May-15 A -177 CSTM2350 Tanking membrane 1 10-May-15 A 10-May-15 A -177 CSTM2360 Backfilling 4 11-May-15 A 14-May-15 A -180 CSTM2370 DI Manhole Cover & Frame 1 15-May-15 A 15-May-15 A -179 CSTM2380 SRC 20 concrete backfill 1 16-May-15 A 16-May-15 A -178 CSTM2390 Benching work 1 17-May-15 A 17-May-15 A -177 CSTM2410 GRP accessories 1 18-May-15 A 18-May-15 A -173 19 12-Apr-15 A 30-Apr-15 A CSTM29290 Excavation & disposal of materials 2 12-Apr-15 A 13-Apr-15 A CSTM29300 Blinding/Tanking & Screeding 3 14-Apr-15 A 16-Apr-15 A CSTM29310 Reinforcement, shuttering, concreting (Base & Wall) 4 17-Apr-15 A 20-Apr-15 A CSTM29320 Pipe connection to manhole & Backdrob 4 21-Apr-15 A 24-Apr-15 A CSTM29330 Bitumen primer 1 25-Apr-15 A 25-Apr-15 A CSTM29340 Tanking membrane 1 26-Apr-15 A 26-Apr-15 A CSTM29350 Backfilling 4 27-Apr-15 A 30-Apr-15 A CSTM29360 DI Manhole Cover & Frame 1 30-Apr-15 A 30-Apr-15 A CSTM29370 SRC 20 concrete backfill 1 30-Apr-15 A 30-Apr-15 A CSTM29380 Benching work 1 30-Apr-15 A 30-Apr-15 A CSTM29390 GRP accessories 1 30-Apr-15 A 30-Apr-15 A SI-2 May Jun Jul -163 -177 Excavation & disposal of materials 2 28-May-15 A 29-May-15 A SI-2 CSTM29420 Blinding/Tanking & Screeding 3 30-May-15 A 01-Jun-15 A SI-2 CSTM29430 Reinforcement, shuttering, concreting (Base & Wall) 4 02-Jun-15 A 05-Jun-15 A SI-2 CSTM29440 Pipe connection to manhole & Backdrob 4 06-Jun-15 A 09-Jun-15 A SI-2 CSTM29450 Bitumen primer 1 10-Jun-15 A 10-Jun-15 A SI-2 Primary Baseline Apr -161 CSTM29410 Remaining Level of Effort Mar 23 28-May-15 A 19-Jun-15 A MANHOLE: 15/1 15/1/28/19/1  Actual Level of Effort 2015 Feb -175 0000.10 MANHOLE: 15/1 15/1/28/19 Total Float SI-1 Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Approved Document Tittle: Progress Update as per Revised Programme 02 Page 18 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish Total Pocess Delays Total Float SI-1 SI-2 CSTM29460 Tanking membrane 1 11-Jun-15 A 11-Jun-15 A SI-2 CSTM29470 Backfilling 4 12-Jun-15 A 15-Jun-15 A SI-2 CSTM29480 DI Manhole Cover & Frame 1 16-Jun-15 A 16-Jun-15 A SI-2 CSTM29490 SRC 20 concrete backfill 1 17-Jun-15 A 17-Jun-15 A SI-2 CSTM29500 Benching work 1 18-Jun-15 A 18-Jun-15 A SI-2 CSTM29510 GRP accessories 1 19-Jun-15 A 19-Jun-15 A SI-2 63 16-Feb-15 A 19-Apr-15 A CSTM2550 Excavation & disposal of materials 2 16-Feb-15 A 17-Feb-15 A -85 CSTM2560 Blinding 2 24-Mar-15 A 25-Mar-15 A -115 CSTM2570 Reinforcement, shuttering, concreting 1 25-Mar-15 A 25-Mar-15 A -111 CSTM2580 Pipe connection to manhole & pre-testing of section 2 28-Mar-15 A 29-Mar-15 A -112 MANHOLE: 15/1 15/1/28/20 Benching work 1 12-Apr-15 A 12-Apr-15 A -143 CSTM2590 Bitumen primer 1 13-Apr-15 A 13-Apr-15 A -143 CSTM2600 Tanking membrane 1 14-Apr-15 A 14-Apr-15 A -143 CSTM2610 Epoxy mortor & sealant 1 15-Apr-15 A 15-Apr-15 A -142 CSTM2620 GRP accessories 1 16-Apr-15 A 16-Apr-15 A -141 CSTM2630 DI Manhole Cover & Frame 1 17-Apr-15 A 17-Apr-15 A -140 CSTM2640 Backfilling 1 18-Apr-15 A 18-Apr-15 A -137 CSTM2650 SRC 20 concrete backfill 1 19-Apr-15 A 19-Apr-15 A -137 66 14-Feb-15 A 20-Apr-15 A -137 CSTM2670 Excavation & disposal of materials 13 14-Feb-15 A 28-Feb-15 A -91 CSTM2680 Blinding 1 12-Mar-15 A 12-Mar-15 A -101 CSTM2690 Reinforcement, shuttering, concreting 2 15-Mar-15 A 16-Mar-15 A -100 CSTM2700 Pipe connection to manhole & pre-testing of section 1 26-Mar-15 A 26-Mar-15 A -107 CSTM27000 Benching work 1 13-Apr-15 A 13-Apr-15 A -140 CSTM2710 Bitumen primer 1 14-Apr-15 A 14-Apr-15 A -140 CSTM2720 Tanking membrane 1 15-Apr-15 A 15-Apr-15 A -140 CSTM2730 Epoxy mortor & sealant 1 16-Apr-15 A 16-Apr-15 A -140 CSTM2740 GRP accessories 1 17-Apr-15 A 17-Apr-15 A -139 CSTM2750 DI Manhole Cover & Frame 1 18-Apr-15 A 18-Apr-15 A -137 CSTM2760 Backfilling 1 19-Apr-15 A 19-Apr-15 A -135 CSTM2770 SRC 20 concrete backfill 1 20-Apr-15 A 20-Apr-15 A -135 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul -139 CSTM25800 MANHOLE: 15/1 15/1/28/21 2015 Feb Approved Document Tittle: Progress Update as per Revised Programme 02 Page 19 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name CSMJ1150 Original Start Duration Jacking GRP lined RC pipe Finish 9 13-Sep-14 A 22-Sep-14 A Total Pocess Delays Testing Prior to Annulus Grouting 1 23-Sep-14 A 23-Sep-14 A -38 CSMJ1160 Annulus grouting 1 24-Sep-14 A 24-Sep-14 A -38 22 23-Sep-14 A 21-Oct-14 A -44 CSMJ1190 Excavation for receiver shaft 9 23-Sep-14 A 02-Oct-14 A -44 CSMJ1200 Concrete for platform & trust wall 1 07-Oct-14 A 07-Oct-14 A -44 CSMJ1210 Jacking GRP lined RC pipe 10 08-Oct-14 A 19-Oct-14 A -44 CSMJ12100 Testing Prior to Annulus Grouting 1 20-Oct-14 A 20-Oct-14 A -44 CSMJ1220 Annulus grouting 1 21-Oct-14 A 21-Oct-14 A -44 MANHOLE CON CONSTRUCTION MANHOLE: 15/1 15/1/28/1 187 25-Sep-14 A 30-Mar-15 A -182 123 27-Nov-14 A 29-Mar-15 A -222 CSMM1840 Preparing shaft for MH construction 2 27-Nov-14 A 29-Nov-14 A -107 CSMM1850 Blinding 1 30-Nov-14 A 30-Nov-14 A -107 CSMM184 Recovery 0 10-Jan-15 A CSMM1860 Reinforcement, shuttering, concreting 44 01-Dec-14 A 21-Jan-15 A CSMM1870 Pipe connection to manhole & pre-testing of section 3 21-Jan-15 A 24-Jan-15 A -146 CSMM18700 Benching work 2 31-Jan-15 A 01-Feb-15 A -151 CSMM1880 Bitumen primer 1 02-Feb-15 A 02-Feb-15 A -151 CSMM1890 Tanking membrane 1 03-Feb-15 A 03-Feb-15 A -151 CSMM1900 Epoxy mortor & sealant 1 04-Feb-15 A 04-Feb-15 A -151 CSMM1930 Backfilling 3 23-Feb-15 A 25-Feb-15 A -159 CSMM1910 GRP accessories 2 25-Feb-15 A 26-Feb-15 A -167 CSMM1920 DI Manhole Cover & Frame 3 23-Mar-15 A 25-Mar-15 A -188 CSMM1940 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -185 -137 122 25-Sep-14 A 19-Feb-15 A 1 25-Sep-14 A 25-Sep-14 A -38 CSMM1960 Blinding 1 27-Sep-14 A 27-Sep-14 A -38 CSMM1970 Reinforcement, shuttering, concreting 96 28-Sep-14 A 21-Jan-15 A -130 CSMM1980 Pipe connection to manhole & pre-testing of section 3 26-Jan-15 A 28-Jan-15 A -134 CSMM19800 Benching work 2 02-Feb-15 A 03-Feb-15 A -137 CSMM1990 Bitumen primer 1 04-Feb-15 A 04-Feb-15 A -137 CSMM2000 Tanking membrane 1 05-Feb-15 A 05-Feb-15 A -137 Remaining Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul -147 Preparing shaft for MH construction  Actual Level of Effort 2015 Feb ery CSMM1950 MANHOLE: 15/1 15/1/28/2 SI-2 -38 CSMJ11500 300mm NOMIN NOMINAL BORE IN M.TUNNEL70m: From MH 15/1/28/3 to MH 15/1/28/4 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 21 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish Total Pocess Delays CSMM2010 Epoxy mortor & sealant 1 07-Feb-15 A 07-Feb-15 A -137 CSMM2020 GRP accessories 2 08-Feb-15 A 09-Feb-15 A -137 CSMM2030 DI Manhole Cover & Frame 2 10-Feb-15 A 11-Feb-15 A -137 CSMM2040 Backfilling 5 14-Feb-15 A 18-Feb-15 A -137 CSMM2050 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/3 1 19-Feb-15 A 19-Feb-15 A -137 103 22-Oct-14 A 21-Feb-15 A -125 CSMJ1840 Preparing shaft for MH construction 1 22-Oct-14 A 22-Oct-14 A -44 CSMJ1850 Blinding 1 23-Oct-14 A 23-Oct-14 A -44 CSMJ1860 Reinforcement, shuttering, concreting 76 25-Oct-14 A 21-Jan-15 A -116 CSMJ1870 Pipe connection to manhole & pre-testing of section 3 31-Jan-15 A 02-Feb-15 A -124 CSMJ18700 Benching work 2 04-Feb-15 A 05-Feb-15 A -125 CSMJ1880 Bitumen primer 1 07-Feb-15 A 07-Feb-15 A -125 CSMJ1890 Tanking membrane 1 08-Feb-15 A 08-Feb-15 A -125 CSMJ1900 Epoxy mortor & sealant 1 09-Feb-15 A 09-Feb-15 A -125 CSMJ1910 GRP accessories 1 10-Feb-15 A 10-Feb-15 A -125 CSMJ1920 DI Manhole Cover & Frame 2 11-Feb-15 A 14-Feb-15 A -125 CSMJ1930 Backfilling 5 15-Feb-15 A 19-Feb-15 A -125 CSMJ1940 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/4 1 21-Feb-15 A 21-Feb-15 A -125 72 05-Jan-15 A 30-Mar-15 A -151 CSMJ1950 Preparing shaft for MH construction 2 05-Jan-15 A 06-Jan-15 A -102 CSMJ1960 Blinding 2 18-Jan-15 A 19-Jan-15 A -112 CSMJ1970 Reinforcement, shuttering, concreting 4 04-Feb-15 A 08-Feb-15 A -125 CSMJ1980 Pipe connection to manhole & pre-testing of section 2 09-Feb-15 A 10-Feb-15 A -125 CSMJ19800 Benching work 2 11-Feb-15 A 14-Feb-15 A -125 CSMJ1990 Bitumen primer 1 15-Feb-15 A 15-Feb-15 A -125 CSMJ2000 Tanking membrane 1 16-Feb-15 A 16-Feb-15 A -125 CSMJ2010 Epoxy mortor & sealant 1 17-Feb-15 A 17-Feb-15 A -125 CSMJ2020 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -131 CSMJ2040 Backfilling 4 24-Feb-15 A 28-Feb-15 A -126 CSMJ2030 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -156 CSMJ2050 SRC 20 concrete backfill REINSTATEMENT Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision 3 28-Mar-15 A 30-Mar-15 A -151 12 16-Mar-15 A 29-Mar-15 A -134 Checked Total Float SI-1 SI-2 2015 Feb Approved Mar Apr May Jun Jul Document Tittle: Progress Update as per Revised Programme 02 Page 22 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration MANHOLE CON CONSTRUCTION Finish Total Pocess Delays 86 17-Dec-14 A 29-Mar-15 A -103 -144 79 27-Dec-14 A 29-Mar-15 A CSMJ2060 Preparing shaft for MH construction 2 27-Dec-14 A 28-Dec-14 A -88 CSMJ2070 Blinding 1 20-Jan-15 A 20-Jan-15 A -107 CSMJ2080 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -115 CSMJ2090 Pipe connection to manhole & pre-testing of section 2 15-Feb-15 A 16-Feb-15 A -123 CSMJ20900 Benching work 2 17-Feb-15 A 18-Feb-15 A -123 CSMJ2100 Bitumen primer 1 19-Feb-15 A 19-Feb-15 A -123 CSMJ2110 Tanking membrane 1 21-Feb-15 A 21-Feb-15 A -123 CSMJ2120 Epoxy mortor & sealant 1 22-Feb-15 A 22-Feb-15 A -123 CSMJ2130 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -125 CSMJ2150 Backfilling 6 22-Feb-15 A 28-Feb-15 A -120 CSMJ2160 SRC 20 concrete backfill 3 25-Mar-15 A 28-Mar-15 A -143 CSMJ2140 DI Manhole Cover & Frame MANHOLE: 15/1 15/1/28/5 MANHOLE: 15/1 15/1/28/6 3 26-Mar-15 A 29-Mar-15 A -150 72 04-Jan-15 A 29-Mar-15 A -137 CSMJ2170 Preparing shaft for MH construction 2 04-Jan-15 A 05-Jan-15 A -88 CSMJ2180 Blinding 2 27-Jan-15 A 28-Jan-15 A -107 CSMJ2190 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -108 CSMJ2200 Pipe connection to manhole & pre-testing of section 2 04-Feb-15 A 05-Feb-15 A -108 CSMJ22000 Benching work 2 07-Feb-15 A 08-Feb-15 A -108 CSMJ2210 Bitumen primer 1 09-Feb-15 A 09-Feb-15 A -108 CSMJ2220 Tanking membrane 1 10-Feb-15 A 10-Feb-15 A -108 CSMJ2230 Epoxy mortor & sealant 1 11-Feb-15 A 11-Feb-15 A -108 CSMJ2240 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -118 CSMJ2260 Backfilling 6 22-Feb-15 A 28-Feb-15 A -113 CSMJ2250 DI Manhole Cover & Frame 3 25-Mar-15 A 28-Mar-15 A -142 CSMJ2270 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/7 3 26-Mar-15 A 29-Mar-15 A -137 75 31-Dec-14 A 29-Mar-15 A -131 -76 CSMJ2300 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A CSMJ2310 Pipe connection to manhole & pre-testing of section 3 05-Jan-15 A 07-Jan-15 A -77 CSMJ23100 Benching work 2 08-Jan-15 A 10-Jan-15 A -77 CSMJ2280 Preparing shaft for MH construction 2 12-Jan-15 A 13-Jan-15 A -89 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Total Float SI-1 SI-2 2015 Feb Approved Mar Apr May Jun Jul Document Tittle: Progress Update as per Revised Programme 02 Page 25 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish Total Pocess Delays CSMJ2320 Bitumen primer 2 13-Jan-15 A 14-Jan-15 A -80 CSMJ2290 Blinding 2 27-Jan-15 A 28-Jan-15 A -101 CSMJ2330 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -93 CSMJ2340 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -93 CSMJ2350 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -112 CSMJ2370 Backfilling 5 23-Feb-15 A 28-Feb-15 A -107 CSMJ2360 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -137 CSMJ2380 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/8 3 26-Mar-15 A 29-Mar-15 A -131 74 01-Jan-15 A 29-Mar-15 A -125 -73 CSMJ2400 Blinding 2 01-Jan-15 A 03-Jan-15 A CSMJ2410 Reinforcement, shuttering, concreting 4 04-Jan-15 A 07-Jan-15 A -73 CSMJ2390 Preparing shaft for MH construction 2 08-Jan-15 A 10-Jan-15 A -80 CSMJ2420 Pipe connection to manhole & pre-testing of section 3 07-Jan-15 A 10-Jan-15 A -73 CSMJ24200 Benching work 2 10-Jan-15 A 11-Jan-15 A -72 CSMJ2430 Bitumen primer 2 11-Jan-15 A 12-Jan-15 A -72 CSMJ2440 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -87 CSMJ2450 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -87 CSMJ2460 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -106 CSMJ2480 Backfilling 6 22-Feb-15 A 28-Feb-15 A -101 CSMJ2470 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -131 CSMJ2490 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/9 3 26-Mar-15 A 29-Mar-15 A -125 86 17-Dec-14 A 29-Mar-15 A -119 CSMJ2510 Blinding 2 17-Dec-14 A 20-Dec-14 A -55 CSMJ2520 Reinforcement, shuttering, concreting 5 22-Dec-14 A 27-Dec-14 A -57 CSMJ2530 Pipe connection to manhole & pre-testing of section 2 29-Dec-14 A 30-Dec-14 A -58 CSMJ25300 Benching work 2 01-Jan-15 A 03-Jan-15 A -59 CSMJ2500 Preparing shaft for MH construction 2 04-Jan-15 A 05-Jan-15 A -70 CSMJ2540 Bitumen primer 2 05-Jan-15 A 06-Jan-15 A -61 CSMJ2550 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -81 CSMJ2560 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -81 CSMJ2570 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -100 CSMJ2590 Backfilling 6 23-Feb-15 A 01-Mar-15 A -96 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Total Float SI-1 SI-2 2015 Feb Approved Mar Apr May Jun Jul Document Tittle: Progress Update as per Revised Programme 02 Page 26 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration CSMJ2580 DI Manhole Cover & Frame CSMJ2600 SRC 20 concrete backfill Finish 3 26-Mar-15 A MANHOLE: 15/1 15/1/28/10 29-Mar-15 A Total Pocess Delays 3 26-Mar-15 A 29-Mar-15 A -119 70 06-Jan-15 A 29-Mar-15 A -112 Preparing shaft for MH construction 2 06-Jan-15 A 07-Jan-15 A -65 CSMJ2620 Blinding 2 27-Jan-15 A 28-Jan-15 A -82 CSMJ2630 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -83 CSMJ2640 Pipe connection to manhole & pre-testing of section 2 04-Feb-15 A 05-Feb-15 A -83 CSMJ26400 Benching work 2 07-Feb-15 A 08-Feb-15 A -83 CSMJ2650 Bitumen primer 1 09-Feb-15 A 09-Feb-15 A -83 CSMJ2660 Tanking membrane 1 10-Feb-15 A 10-Feb-15 A -83 CSMJ2670 Epoxy mortor & sealant 1 11-Feb-15 A 11-Feb-15 A -83 CSMJ2680 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -93 CSMJ2700 Backfilling 6 22-Feb-15 A 28-Feb-15 A -88 CSMJ2690 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -118 CSMJ2710 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -112 33 13-Jan-15 A 21-Feb-15 A -72 CSMJ2720 Preparing shaft for MH construction 2 13-Jan-15 A 14-Jan-15 A -62 CSMJ2730 Blinding 2 27-Jan-15 A 28-Jan-15 A -73 CSMJ2750 Pipe connection to manhole & pre-testing of section 2 31-Jan-15 A 01-Feb-15 A -70 CSMJ2740 Reinforcement, shuttering, concreting 5 28-Jan-15 A 02-Feb-15 A -73 CSMJ27500 Benching work 2 02-Feb-15 A 03-Feb-15 A -70 CSMJ2760 Bitumen primer 1 04-Feb-15 A 04-Feb-15 A -70 CSMJ2770 Tanking membrane 1 05-Feb-15 A 05-Feb-15 A -70 CSMJ2780 Epoxy mortor & sealant 1 07-Feb-15 A 07-Feb-15 A -70 CSMJ2790 GRP accessories 1 08-Feb-15 A 08-Feb-15 A -70 CSMJ2800 DI Manhole Cover & Frame 2 09-Feb-15 A 10-Feb-15 A -70 CSMJ2810 Backfilling 5 11-Feb-15 A 17-Feb-15 A -70 CSMJ2820 SRC 20 concrete backfill MANHOLE: 15/1 15/1/28/12 CSMJ2830 Beaking MH and Pipe connection REINSTATEMENT ASPHALT Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision 2 19-Feb-15 A 21-Feb-15 A -72 3 16-Mar-15 A 18-Mar-15 A -109 -109 3 16-Mar-15 A 18-Mar-15 A 11 16-Mar-15 A 28-Mar-15 A -85 3 25-Mar-15 A 28-Mar-15 A -89 Checked SI-2 2015 Feb Mar Apr May Jun Jul -125 CSMJ2610 MANHOLE: 15/1 15/1/28/11 Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 27 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration CSMTR1360 90mm Base course CSMTR1370 70mm Wearing course Finish 3 25-Mar-15 A PAVING/ CONCRETE PAVING PAVING/CONCR 28-Mar-15 A Total Pocess Delays 3 25-Mar-15 A 28-Mar-15 A -89 2 16-Mar-15 A 17-Mar-15 A -76 Formation preparation 2 16-Mar-15 A 17-Mar-15 A -77 CSMTR1420 Paving interlock 2 16-Mar-15 A 17-Mar-15 A -76 -76 1 16-Mar-15 A 16-Mar-15 A CSMTR1380 Excavation & concrete foundation for kerbs 1 16-Mar-15 A 16-Mar-15 A -78 CSMTR1400 Backing concrete 1 16-Mar-15 A 16-Mar-15 A -76 CSMTR1390 Kerbs installation PLANT AND GR GRASS 1 16-Mar-15 A 16-Mar-15 A -77 2 16-Mar-15 A 17-Mar-15 A -76 CSMTR1430 Excavation for plants 2 16-Mar-15 A 17-Mar-15 A -76 CSMTR1440 Planting/grass 2 16-Mar-15 A 17-Mar-15 A -76 162 08-Jan-15 A 18-Jun-15 A -184 159 11-Jan-15 A 18-Jun-15 A -184 144 11-Jan-15 A 03-Jun-15 A -170 54 11-Jan-15 A 15-Mar-15 A -87 -37 HOUSE CONNECT CONNECTION SEWER IN TRENCH TREN (AREA) HOUSE CONNE CONNECTION PHASE 1 SURVEY AND D DEMOLISH CHG1000 Plot survey 2 11-Jan-15 A 12-Jan-15 A CHG1010 Demolition of ext. underground structures 3 12-Mar-15 A 15-Mar-15 A -87 67 24-Feb-15 A 01-May-15 A -242 -232 PIPE WORK WORK IN IN TRENCH-HC 01 CSHCP1010 Excavation & disposal of materials 43 24-Feb-15 A 07-Apr-15 A CSHCP1020 Bedding preparation prior to pipe laying 43 26-Feb-15 A 09-Apr-15 A -231 CSHCP1030 Laying pipe & connecting to new manhole 42 28-Feb-15 A 10-Apr-15 A -228 CSHCP1040 Granular & concrete surrounds 44 28-Feb-15 A 12-Apr-15 A -227 CSHCP1050 Backfilling 46 28-Feb-15 A 14-Apr-15 A -227 CSHCP1060 Concrete backfill -242 PIPE WORK WORK IN IN TRENCH-HC 02 63 28-Feb-15 A 01-May-15 A 70 28-Feb-15 A 08-May-15 A 29-Mar-15 A CSHCP1070 Excavation & disposal of materials 30 28-Feb-15 A CSHCP1080 Bedding preparation prior to pipe laying 43 28-Feb-15 A 11-Apr-15 A CSHCP1090 Laying pipe & connecting to new manhole 50 28-Feb-15 A 18-Apr-15 A CSHCP1100 Granular & concrete surrounds 52 28-Feb-15 A 20-Apr-15 A CSHCP1110 Backfilling 54 28-Feb-15 A 22-Apr-15 A CSHCP1120 Concrete backfill 70 28-Feb-15 A 08-May-15 A Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked SI-2 2015 Feb Mar Apr May Jun Jul -91 CSMTR1410 KERBSTONE Total Float SI-1 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 28 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration PIPE WORK WORK IN IN TRENCH-HC 03 Finish 98 24-Feb-15 A 01-Jun-15 A Total Pocess Delays CSHCP1130 Excavation & disposal of materials 86 24-Feb-15 A 22-May-15 A CSHCP1140 Bedding preparation prior to pipe laying 84 26-Feb-15 A 24-May-15 A Ps CSHCP1150 Laying pipe & connecting to new manhole 84 26-Feb-15 A 26-May-15 A Ps CSHCP1160 Granular & concrete surrounds 84 26-Feb-15 A 28-May-15 A Ps CSHCP1170 Backfilling 50 07-Apr-15 A 30-May-15 A Ps CSHCP1180 Concrete backfill 99 25-Feb-15 A 03-Jun-15 A 13-Apr-15 A CSHCP1190 Excavation & disposal of materials 48 25-Feb-15 A CSHCP1200 Bedding preparation prior to pipe laying 49 26-Feb-15 A 15-Apr-15 A CSHCP1210 Laying pipe & connecting to new manhole 51 26-Feb-15 A 17-Apr-15 A CSHCP1220 Granular & concrete surrounds 53 26-Feb-15 A 19-Apr-15 A CSHCP1230 Backfilling 53 28-Feb-15 A 21-Apr-15 A CSHCP1240 Concrete backfill INSPECTION CHAMBER INSPECTION C 1 2 02-Jun-15 A 03-Jun-15 A 21 14-Apr-15 A 04-May-15 A 1 14-Apr-15 A 14-Apr-15 A -133 Blinding 1 15-Apr-15 A 15-Apr-15 A -133 CHCC1030 Reinforcement, shuttering, concreting 1 16-Apr-15 A 16-Apr-15 A -132 CHCC1040 Pipe connection to manhole & pre-testing of section 1 17-Apr-15 A 17-Apr-15 A -132 CHCC10400 Benching work 1 18-Apr-15 A 18-Apr-15 A -130 CHCC1050 Bitumen primer 1 19-Apr-15 A 19-Apr-15 A -130 CHCC1060 Tanking membrane 1 20-Apr-15 A 20-Apr-15 A -130 CHCC1070 Epoxy mortor & sealant 1 21-Apr-15 A 21-Apr-15 A -130 CHCC1080 GRP accessories 1 22-Apr-15 A 22-Apr-15 A -130 CHCC1090 DI Manhole Cover & Frame 1 03-May-15 A 03-May-15 A -139 CHCC1100 Backfilling 1 04-May-15 A 04-May-15 A -139 44 15-Apr-15 A 28-May-15 A CHCC1120 Excavation & disposal of materials 1 15-Apr-15 A 15-Apr-15 A -134 CHCC1130 Blinding 1 16-Apr-15 A 16-Apr-15 A -134 CHCC1140 Reinforcement, shuttering, concreting 1 17-Apr-15 A 17-Apr-15 A -133 CHCC1150 Pipe connection to manhole & pre-testing of section 1 18-Apr-15 A 18-Apr-15 A -133 CHCC11500 Benching work 1 03-May-15 A 03-May-15 A -145 Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Apr May Jun Jul Ps Excavation & disposal of materials Remaining Level of Effort Mar -139 CHCC1020  Actual Level of Effort 2015 Feb Ps CHCC1010 INSPECTION CHAMBER INSPECTION C 2 SI-2 Ps 2 31-May-15 A 01-Jun-15 A PIPE WORK WORK IN IN TRENCH-HC 04 Total Float SI-1 -163 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 29 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish 1 23-May-15 A 23-May-15 A Total Pocess Delays CHCC1160 Bitumen primer CHCC1170 Tanking membrane 1 24-May-15 A 24-May-15 A -164 Ps CHCC1180 Epoxy mortor & sealant 1 25-May-15 A 25-May-15 A -164 Ps CHCC1190 GRP accessories 1 26-May-15 A 26-May-15 A -164 Ps CHCC1200 DI Manhole Cover & Frame 1 27-May-15 A 27-May-15 A -163 Ps CHCC1210 Backfilling 1 28-May-15 A 28-May-15 A -163 Ps CHCC11510 Excavation & disposal of materials 1 03-May-15 A 03-May-15 A CHCC11520 Blinding 1 04-May-15 A CHCC11530 Reinforcement, shuttering, concreting 1 05-May-15 A 05-May-15 A CHCC11540 Pipe connection to manhole & pre-testing of section 1 06-May-15 A 06-May-15 A CHCC11550 Benching work 1 07-May-15 A 07-May-15 A CHCC11560 Bitumen primer 1 08-May-15 A 08-May-15 A CHCC11570 Tanking membrane 1 09-May-15 A 09-May-15 A CHCC11580 Epoxy mortor & sealant 1 10-May-15 A 10-May-15 A CHCC11590 GRP accessories 1 11-May-15 A CHCC11600 DI Manhole Cover & Frame 1 12-May-15 A 12-May-15 A CHCC11610 Backfilling Apr May Jun Jul -164 Ps 11-May-15 A 14-May-15 A Excavation & disposal of materials 1 17-Apr-15 A 17-Apr-15 A CHCC11630 Blinding 1 18-Apr-15 A 18-Apr-15 A CHCC11640 Reinforcement, shuttering, concreting 1 04-May-15 A 04-May-15 A CHCC11650 Pipe connection to manhole & pre-testing of section 1 05-May-15 A 05-May-15 A CHCC11660 Benching work 1 06-May-15 A 06-May-15 A CHCC11670 Bitumen primer 1 07-May-15 A 07-May-15 A CHCC11680 Tanking membrane 1 08-May-15 A 08-May-15 A CHCC11690 Epoxy mortor & sealant 1 09-May-15 A 09-May-15 A CHCC11700 GRP accessories 1 10-May-15 A 10-May-15 A CHCC11710 DI Manhole Cover & Frame 1 11-May-15 A CHCC11720 Backfilling 1 14-May-15 A 14-May-15 A REINSTATEMENT FOR CHAMBERS REINSTATEME Primary Baseline Mar 04-May-15 A CHCC11620 Reinstatement around constructed chamber Remaining Level of Effort 2015 Feb 1 13-May-15 A 13-May-15 A 28 17-Apr-15 A INSPECTION CHAMBER INSPECTION C 4  Actual Level of Effort SI-2 11 03-May-15 A 13-May-15 A INSPECTION CHAMBER INSPECTION C 3 CHCC1220 Total Float SI-1 Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision 11-May-15 A 1 31-May-15 A 31-May-15 A -165 1 31-May-15 A 31-May-15 A -165 Checked Approved Document Tittle: Progress Update as per Revised Programme 02 Page 30 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration HOUSE CONNE CONNECTION PHASE 2 SURVEY AND D DEMOLISH Finish 128 21-Jan-15 A 28-May-15 A 125 21-Jan-15 A 25-May-15 A C.HC.P221000 Plot survey 3 21-Jan-15 A C.HC.P221010 Demolition of ext. underground structures 3 23-May-15 A 25-May-15 A 94 24-Feb-15 A 28-May-15 A Excavation & disposal of materials 75 24-Feb-15 A 09-May-15 A CSHCP1260 Bedding preparation prior to pipe laying 76 25-Feb-15 A 11-May-15 A CSHCP1270 Laying pipe & connecting to new manhole 79 24-Feb-15 A 13-May-15 A CSHCP1280 Granular & concrete surrounds 81 24-Feb-15 A 15-May-15 A CSHCP1290 Backfilling 82 25-Feb-15 A 17-May-15 A CSHCP1300 Concrete backfill 93 25-Feb-15 A 28-May-15 A INSPECTION CHAMBER INSPECTION C 5 0 REINSTATEMENT FOR CHAMBERS REINSTATEME 2 25-May-15 A C.HC.P221020 Reinstatement around constructed chamber Total Float SI-1 SI-2 SURVEY AND D DEMOLISH 148 22-Jan-15 A 18-Jun-15 A -184 108 22-Jan-15 A 09-May-15 A -157 24-Jan-15 A Plot survey 2 22-Jan-15 A Demolition of ext. underground structures 3 07-May-15 A 09-May-15 A 13 26-May-15 A 07-Jun-15 A PIPE WORK WORK IN IN TRENCH-HC 06 -177 5 26-May-15 A 30-May-15 A CSTH1020 Bedding preparation prior to pipe laying 2 31-May-15 A 01-Jun-15 A -182 CSTH1030 Laying pipe & connecting to new manhole 4 02-Jun-15 A 05-Jun-15 A -182 CSTH1050 Backfilling 2 06-Jun-15 A 07-Jun-15 A -179 CSTH1060 Concrete backfill 2 06-Jun-15 A 07-Jun-15 A -177 CSTH1040 Granular & concrete surrounds 2 06-Jun-15 A 07-Jun-15 A -183 -181 11 31-May-15 A 10-Jun-15 A PIPE WORK WORK IN IN TRENCH-HC 07 (SI 2) CSTH12410 Excavation & disposal of materials 5 31-May-15 A 04-Jun-15 A CSTH12420 Bedding preparation prior to pipe laying 2 05-Jun-15 A 06-Jun-15 A SI-2 CSTH12430 Laying pipe & connecting to new manhole 2 07-Jun-15 A 08-Jun-15 A SI-2 CSTH12440 Granular & concrete surrounds 2 07-Jun-15 A 08-Jun-15 A SI-2 CSTH12460 Concrete backfill 2 09-Jun-15 A 10-Jun-15 A SI-2 CSTH12450 Backfilling 2 09-Jun-15 A 10-Jun-15 A SI-2 Remaining W ork Jul -45 Excavation & disposal of materials Primary Baseline Jun -155 CSTH1010 Second Baseline May 0 CSTH1080  Actual Work Apr 26-May-15 A CSTH1070 Remaining Level of Effort Mar 2 25-May-15 A 26-May-15 A HOUSE CONNE CONNECTION PHASE 3  Actual Level of Effort 2015 Feb 24-Jan-15 A CSHCP1250 PIPE WORK WORK IN IN TRENCH-HC 05 Total Pocess Delays Criti... Mile... Date Revision Checked SI-2 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 31 of 35 Data Date: 22-Jun-15 Aug Project ID: IAD-HC13/14C076G. Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)  Activity ID Activity Name Original Start Duration Finish 13 05-Jun-15 A INSPECTION CHAMBER INSPECTION C 1 (SI 2) 17-Jun-15 A Total Pocess Delays Total Float SI-1 SI-2 Excavation & disposal of materials 1 05-Jun-15 A 05-Jun-15 A -183 SI-2 CSTH1110 Blinding 1 06-Jun-15 A 06-Jun-15 A -183 SI-2 CSTH1120 Reinforcement, shuttering, concreting 2 07-Jun-15 A 08-Jun-15 A -182 SI-2 CSTH1130 Pipe connection to manhole & pre-testing of section 1 09-Jun-15 A 09-Jun-15 A -182 SI-2 CSTH11300 Benching work 2 10-Jun-15 A 11-Jun-15 A -182 SI-2 CSTH1140 Bitumen primer 1 12-Jun-15 A 12-Jun-15 A -182 SI-2 CSTH1150 Tanking membrane 1 13-Jun-15 A 13-Jun-15 A -182 SI-2 CSTH1160 Epoxy mortor & sealant 1 14-Jun-15 A 14-Jun-15 A -181 SI-2 CSTH1170 GRP accessories 1 15-Jun-15 A 15-Jun-15 A -181 SI-2 CSTH1180 DI Manhole Cover & Frame 1 16-Jun-15 A 16-Jun-15 A -181 SI-2 CSTH1190 Backfilling 1 17-Jun-15 A 17-Jun-15 A -181 SI-2 -182 13 06-Jun-15 A 18-Jun-15 A CSTH1210 Excavation & disposal of materials 1 06-Jun-15 A 06-Jun-15 A -184 SI-2 CSTH1220 Blinding 1 07-Jun-15 A 07-Jun-15 A -184 SI-2 CSTH1230 Reinforcement, shuttering, concreting 2 08-Jun-15 A 09-Jun-15 A -183 SI-2 CSTH1240 Pipe connection to manhole & pre-testing of section 1 10-Jun-15 A 10-Jun-15 A -183 SI-2 CSTH12400 Benching work 2 11-Jun-15 A 12-Jun-15 A -183 SI-2 CSTH1250 Bitumen primer 1 13-Jun-15 A 13-Jun-15 A -183 SI-2 CSTH1260 Tanking membrane 1 14-Jun-15 A 14-Jun-15 A -183 SI-2 CSTH1270 Epoxy mortor & sealant 1 15-Jun-15 A 15-Jun-15 A -182 SI-2 CSTH1280 GRP accessories 1 16-Jun-15 A 16-Jun-15 A -182 SI-2 CSTH1290 DI Manhole Cover & Frame 1 17-Jun-15 A 17-Jun-15 A -182 SI-2 CSTH1300 Backfilling 1 18-Jun-15 A 18-Jun-15 A -182 SI-2 5 14-Jun-15 A 18-Jun-15 A -182 5 14-Jun-15 A 18-Jun-15 A -182 141 08-Jan-15 A 28-May-15 A -163 141 08-Jan-15 A 28-May-15 A -163 97 08-Jan-15 A 14-Apr-15 A -132 REINSTATEMENT FOR CHAMBERS (SI 2) REINSTATEME CSTH1310 Reinstatement around constructed chamber SEWER IN MICT MICTROTUNNEL HOUSE CONNE CONNECTION PHASE 2 SURVEY AND D DEMOLISH CSMTHC1390 Plot survey 2 08-Jan-15 A 10-Jan-15 A -33 CSMTHC1400 Demolition of ext. underground structures 3 12-Apr-15 A 14-Apr-15 A -130 88 22-Feb-15 A 22-May-15 A -158 PIPE WORK WORK IN IN TRENCH-HC 12/13 Remaining Level of Effort  Actual Level of Effort Primary Baseline Second Baseline  Actual Work Remaining W ork Criti... Mile... Date Revision Checked Mar Apr May Jun Jul -181 CSTH1100 INSPECTION CHAMBER INSPECTION C 2 (SI 2) 2015 Feb SI-2 Approved Document Tittle: Progress Update as per Revised Programme 02 Page 32 of 35 Data Date: 22-Jun-15 Aug